1.Install the PRO22ULPS (Altronix AL400ULX) power supply and battery enclosure per the supplied instructions.
2.Measure and install four mounting screws with heads smaller than .4" (1cm) using proper techniques for the material on which the PRO22ENC1 or PRO22ENC2 is being mounted. Use a rectangular screw pattern 12.1" H x 16" W (0.307m H x 0.4064m W). Leave the screws exposed approximately 1/2" (1.27cm).
3.Open the door of the enclosure and place the hanging slots over the mounting screws. Push the enclosure over the mounting screws and allow the screws to slide into the slots. Finish tightening the mounting screws to securely hold the enclosure.
4.Run all appropriate wiring to the case. All cable shields should tie to the grounding lug found on the top of the enclosure.
5.Install the required panels into the runners. The PRO22IC should be placed in the
6.Wire the readers, input and output connections.
7.CHECK ALL CONNECTIONS PRIOR TO POWERING UP THE ENCLOSURE AND PANELS.
8.Wire the 12VDC, AC Fail, Battery Fail and tamper switch from the AL400ULX to the enclosure. Make sure that the power supply is not powered up at the time.
9.Wire the 12VDC to the Panel on the far right first making sure that the polarity of the wires are correct.
10.Wire the tamper switch, AC Fail and Battery Fail to assigned inputs.
11.Wire the PRO22ENC1 or PRO22ENC2 tamper switch to the tamper input located on the first panel on the right.
12.The remainder of the panels can be manually wired for power and
They may also be wired using the Auxiliary Rack Harness purchased with the equip- ment. This will reduce wiring time in the field since the power and
13.CHECK ALL CONNECTIONS PRIOR TO POWERING UP THE ENCLOSURE AND PANELS.
14.Wire the TCP/IP connection to the network HUB.