New Buck Corporation FS 21 installation instructions Final Check

Page 18

FINAL CHECK

1.Recheck the specified clearances.

2.Remove all foreign material from the firebox area.

3.Open the primary air draft.

4.Plug the power cord into a 115V AC outlet when using with optional motor.

5.Place crumpled pieces of newspaper in the stove. Light it and close the doors. Ensure that the stove draws properly through the primary draft.

6.Check for smoke leaks around the door.

CAUTION

Open the doors and check for smoke escaping from the front of the stove. Smoking usually indicates a defective or poorly positioned chimney. Some chimneys with a marginal draft can be preheated by lighting newspaper and holding it near the open damper with a poker or fire tong. Once the chimney heats up, a proper draft can usually be obtained.

If a thorough review of the Troubleshooting Guide in the rear of the manual does not reveal the problem, contact your dealer for assistance.

CAUTION

The unit is painted with a specially formulated high temperature paint that cures during the first two or three firings. You may notice a slight smoking effect and an odor of burning paint when you build the first fires. This is normal and is not a cause for alarm. In some cases, these fumes will activate a smoke alarm. Opening a window near the unit will allow these fumes to escape. DO NOT build a large, roaring fire until this curing is complete or the heater finish may be damaged.

Page 16

Image 18
Contents Model FS NON-CATALYTIC Unit Page Table of Contents INSTALLATION, OPERATION, Maintenance Instructions Model FS Read this First Important InstructionsSection IntroductionPreparing the Stove for Installation ChimneyFloor Protection Preparing the Room Heater Location Model HOW to Locate Chimney Exit and Install 15.5 Residential and Mobile Home Installation C D E F G HOW to Locate Chimney Exit and Install Chimney Reefer to MANUFACTURER’S Installation Instruction OUT Side AIR Installation Tools for InstallationFlashing Final Check Section Alcove Installation Clearances Floor Protection Alcove Installation Alcove Installation Clearances Final Check Page Section Operation Building a FireASH Removal Instructions Sure to Turn Blower OFF Before Removing AshesPage Step Wire Diagram #10 16 X 1/2 HEX Head #6 32 X 1/2 Slot Head Screw Section Wood Heater Safety Section Troubleshooting Problem Possible Cause SolutionWarranty Time Periods ProcedureProducts Covered Conditions and Exclusions Other RightsOwner Registration Card