GSW 5065 manual Water Supply, Piping Installation

Page 15

4.Tighten the upper gear clamp to ensure the vent pipe is firmly secured and gas tight.

5.Check that the lower gear clamp is firmly seated, secured and gas tight.

6.As a final check, the vent pipe should be gently moved side to side and vertically. There should be no slippage or movement of the vent pipe within the coupling.

7.Seal around the termination assembly where it passes through the wall, inside and out, with silicone sealant.

WATER

SUFFIX

VENT PIPE

PRESSURE

* VENT

MAXIMUM EQUIVALENT

MINIMUM EQUIVALENT

HEATER

SWITCH

MATERIAL

MODEL

 

SIZE

SETTING

(SCHEDULE 40)

VENT LENGTH

VENT LENGTH

 

 

 

 

G/JW40,

NVH,

50mm (2 in.)

- 0.15 in. w.c.

ABS, PVC**,

15.2m (50 ft.) +

0.76m (2.5 ft.) + one 90°

PVH

 

(-0.037 kPa)

CPVC

termination elbow

elbow + termination elbow

50

NVH,

76mm (3 in.)

- 0.15 in. w.c.

ABS, PVC**,

24.4m (80 ft.) +

15.2m (50 ft.) +

 

 

PVH

 

(-0.037 kPa)

CPVC

termination elbow

termination elbow

G/JW5065

SNV,

76mm (3 in.)

- 0.55 in. w.c.

ABS, PVC,

15.2m (50 ft.) +

0.91m (3 ft.) + one 90°

 

SPV

 

(-.137 kPa)

CPVC

termination elbow

elbow + termination elbow

G/JW5065

LNV

76mm (3 in.)

- 0.50 in. w.c.

ABS, PVC,

19.8m (65 ft.) +

6.9m (20 ft.) + termination

 

 

 

(-.124 kPa)

CPVC

termination elbow

elbow

Notes:

1. Each 50mm (2 in.), 90° long radius elbow is equivalent to 1.5m (5 ft.) of vent length.

2. Each 76mm (3 in.), 90° long radius elbow is equivalent to 2.1m (7 ft.) of vent length.

3. Each 50mm (2 in.), 45° long-radius elbow is equivalent to 0.9m (3 ft.) of vent length.

4. Each 76mm (3 in.), 45° long radius elbow is equivalent to 1.2m (4 ft.) of vent length.

5. Minimum distance between elbows is 150mm (6 in.).

6. Do not mismatch venting materials. *Check local codes to determine which materials are allowed in your area.

7. **Pipe assembly adaptor must be used with PVC venting material (see Figure 14). Table 2 Allowable Vent Lengths and Materials (Vert. and Horiz.).

Water Supply

 

 

 

 

 

 

 

 

 

 

 

 

 

 

lations where the water pressure is high. The pressure-

Piping Installation

 

 

 

 

 

 

 

 

 

 

 

 

 

 

reducing valve should be located on the supply to the entire

Piping, fittings, and valves should be installed according to

house in order to maintain equal hot and cold water pres-

the installation drawing (Figure 17). A pressure-reducing

sure.

valve and/or an expansion tank may be required for instal-

Important:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Do not apply heat to the water fittings on the heater as

 

 

IN A CLOSED SYSTEM USE EITHER: 1.THERMAL EXPANSION TANK

 

 

 

 

 

 

 

 

 

 

OR

 

they may contain nonmetallic parts. If solder connections

 

 

 

 

 

 

 

2.PRESSURE RELIEF VALVE.

 

are used, solder the pipe to an adaptor before attaching

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

HOT

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

the adaptor to the hot and cold water fittings.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Some models may contain energy saving heat traps to

 

WATER

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

OUTLET

NOTE: BLOWER

 

 

 

 

 

 

 

 

 

 

prevent the circulation of hot water within the pipes. Do

 

ASSEMBLY NOT

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

SHOWN FOR

 

 

 

 

 

 

 

 

 

not remove the inserts within the heat traps.

 

 

 

 

PRESSURE

 

 

UNION

 

 

 

 

 

 

 

 

 

 

CLARITY.

 

 

REDUCING

 

 

 

 

 

Always use a proper grade of joint compound and be

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

VALVE

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

WITH

 

 

 

 

 

 

certain that all fittings are drawn up tight.

 

 

 

 

 

 

 

 

 

 

BYPASS

 

 

 

 

 

1.

Install the water piping and fittings as shown in Figure

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

COLD WATER

 

 

COLD WATER

 

 

17. Connect the cold water supply to the fitting (3/4”

 

 

 

 

 

 

INLET VALVE

 

 

INLET

 

 

 

 

 

 

 

 

 

 

 

 

NPT) marked “COLD” (or “C”). Connect the hot water

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

supply to the fitting (3/4” NPT) marked “HOT” (or “H”).

 

 

 

 

 

 

TEMPERATURE AND

 

 

 

 

 

 

 

PRESSURE RELIEF VALVE

 

 

 

 

2.

The installation of unions in both the hot and cold water

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

supply lines is recommended.

 

 

 

 

 

 

 

DISCHARGE LINE 300mm

3.

 

 

 

 

 

 

 

(12 in.) max (CANADA) OR

 

The manufacturer of this water heater recommends

 

 

 

 

 

 

 

150mm (6 in.) max (U.S.)

 

 

installing a tempering valve in the domestic hot water

 

 

 

 

 

 

 

ABOVE DRAIN

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

line as shown in Figure 18. These valves reduce the

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

MASSACHUSETTS: INSTALL A

 

 

point-of-use water temperature by mixing cold and hot

 

 

 

 

VACUUM RELIEF IN COLD WATER

 

 

water. Contact a licensed plumber or the local plumbing

 

 

 

 

LINE PER SECTION 19MGL 142

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

authority.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4.

If installing the water heater in a closed water system,

 

 

 

 

 

 

 

 

DRAIN PAN CONNECT TO

 

 

 

 

 

 

 

 

PROPERLY OPERATING

 

 

install an expansion tank in the cold water line as spec-

 

 

 

 

 

 

 

 

FLOOR DRAIN.

 

 

ified under “Closed System/Thermal Expansion”.

 

Figure 17 Water Piping Installation

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

15 –

 

Image 15
Contents What to do if YOU Smell GAS For Your SafetyPage Table of Contents Consumer Responsibilities IntroductionSafety Warning Flammable Vapours II SafetyFor Installations in Canada For Installations in the United StatesRelief Valve Requirements T&P Location RequirementsValves For Hot Water Supply Systems, Ansi Z21.22/CSA Earthquake Zones Clearances and AccessibilityGas Pressure Gas Leak TestingCanadian Installations Air RequirementsConfined Space Air Requirements for Installations Do not use near flame or open fire VentingUse of Solvent Cement and Primer Use only in well-ventilated areasVertical Vent Terminal Installation Horizontal Vent Terminal InstallationsParts must fit well and not put stress on any sections Vent Pipe InstallationVent Pipe Runs Vent Pipe Connection to BlowerRubber Coupling Connection Water Supply Piping InstallationDo not plug valve Temperature Pressure reliefValve Is dripping Or leaking, have a Licensed plumber repair itOr National Electrical Code Nfpa 70 U.S.A Temperature and Pressure Relief ValveElectrical Supply Electrical Code CAN/CSA C22.1, Part I CanadaFlammable Vapour Sensor exploded view Installation Checklist QUE Faire SI Vous Sentez UNE Odeur DE GAZ Operating Instructions Instructions DE Mise EN MarcheIf You Do Not Smell Gas When heater is ready to be put into serviceGas Control/Thermostat What to Do If You Smell GasTemperature Regulation Flammable Vapour SensorRisk of scalding Emergency Shut Down Water Heater OperationKeep the area around the heater clear UnobstructedRoutine Preventative Maintenance VI MaintenanceDraining and Flushing Replacement Parts VII Combo HeatingKeep the area around the heater clear and unobstructed Combo Heating Air Handler Combo Heating Baseboard InstallationSymptom Possible Causes Corrective Action Viii Troubleshooting Guide Robertshaw 2000WDERItems not supplied with the water heater IX Parts Reference Illustration~ Certificate of Warranty ~