Woodstock W1823 manual Assembly, To assemble the dust collector, do these steps

Page 16

Model W1823 (Mfg. Since 9/10)

SETUP

Assembly

Before beginning assembly, refer to the inventory list and group all fasteners with their intended components. Doing this will make assembly easier.

When assembling this machine, tighten fasteners using hand tools only. Avoid using air or electric impact tools because fasteners can easily be over-tightened, causing them to dig into the paint, strip threads, and over- compress gaskets—causing flanges to deform and leak. Using silicone sealant at connection points is optional.

To assemble the dust collector, do these steps:

1.With the help of another person, place the blower housing on its side carefully as not to scratch the paint.

2.Fasten the three upper legs to the leg support bosses on the blower housing with (12) 516"-18 x 12" button head cap screws, as shown in Figure 9.

3.Thread the caster wheels into the lower legs and tighten.

4.Insert and fasten the leg connectors in the lower legs using (12) 516"-18 x 12" button head cap screws, as shown in Figure 10.

Leg Support

 

Boss

 

 

Blower

 

Housing

Upper Leg

Button

 

 

Head

 

Cap

 

Screw

Figure 9. Upper leg installed on blower

housing leg support boss.

Figure 10. Lower leg connector and swivel

caster installation.

5.Insert the leg connectors into the upper legs, as shown in Figure 11, and secure together with (12)

516"-18 x 12" button head cap screws.

Note: You will notice that the bolt pattern in the upper legs and the leg connectors (Figure 11) is off–center to ensure that the lower legs can only be installed in the correct direction.

Upper Leg

Leg

Lower Leg

Connector

Figure 11. Inserting a lower leg into an

upper leg.

-14-

Image 16
Contents OWNERS MANUAL Page Contents Woodstock Technical Support IntroductionMachine Description Controls and Features Left side viewB68=C HE886IDCH `gg`e`d\ej`fej Xikfe SAFETYJ8=KP ZXlj\XdX\kfk\dXZ`e\ip%Safety Additional Safety for Dust Collectors Circuit Requirements for 110V Prewired ElectricalCircuit Requirements Full-Load Current RatingFor 110V Connection Prewired For 220V Connection Must be RewiredGrounding Requirements Extension CordsUnpacking SetupInventory Hardware and Tool Bag Inventory Figure Qty Canister Inventory Figure QtyMachine Placement Assembly To assemble the dust collector, do these stepsSetup Vacuum tube installed Screw Collection lid installation Canister bag installed Test Run To test run the machine, do these stepsCollection System System SetupTips for Optimum Performance Duct Material Metal DuctFlexible Duct Plastic DuctSystem Grounding Flex-hose grounded to Machine Plastic BlastOperations General OperationRemote Control Operation Remote control receiver Hour Intervals BackCyclone Dust Collector Accessories Black ABS Plastic Blast Gates Aluminum Blast GatesMaintenance Normal Filter CleaningGeneral Emptying DrumService Major Filter CleaningRemote Control Reprogramming To reprogram the remote control, do these stepsElectrical Safety Instructions  HL8C@=@CKI@@8E% Due toCKI@8CIHL@IDEKJ% You Must @I&FDGFEEK8D8% DamagedWiring Diagram Stop220V Conversion To convert the Model W1823 to 220V, do these stepsMagnetic switch box Troubleshooting Problem Possible CauseOpen 1 or 2 more blast gates to different branch Parts Main Parts List DescriptionLabel Placement Model W1823 Mfg. Since 9/10 Place Stamp Here Warranty =\FjVainBVXcZhVcYIddah