16. With the cyclone funnel port still open for access to the hex nuts inside, fasten the ends of the lift cables to the outside of the cyclone funnel, as shown in Figure 18, using the pre-installed hex bolts.

17.

Slide the 7" hose clamps onto the ports of the

 

 

 

Lift Cable

 

 

 

 

End

 

 

 

 

collection drum lid and the cyclone funnel (see

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Figure 18).

 

 

 

 

 

 

 

 

Tip: You can disassemble the hose clamps for more

 

 

 

 

 

 

 

 

clearance to get the clamps positioned over the

 

 

 

 

 

 

 

 

hose. To reassemble the clamps, refer to Figure 19.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

18.

Work the 7" hose onto both ports, position the hose

 

 

Figure 18. Collection lid installation.

 

 

 

 

 

 

 

clamps on the hose, then tighten them.

19.Connect the ground wire between the drum cover and leg with the included (2) 516"-18 x 12" flange screws, as shown in Figure 20. This wire prevents accumulation of static electricity at the collection drum.

20.Position the lift cable in the wheel grooves.

Figure 19. Correct hose clamp assembly.

Flange

Screws

Ground Wire

Ground Screw

SETUP

21.Lower the lid release lever and verify that the lower edge of the lid flange is approximately 25⁜12" above the floor, as shown Figure 21 so the dust collection drum can be rolled under the dust collector without interference from the lid.

If the drum hits the lid when it is raised, loosen the hose and reposition the lid higher. Do not attempt to adjust the cables.

Figure 20. Ground wire location.

Release

Lever

Figure 21. Checking collection lid lift.

-17-

Image 19
Contents OWNERS MANUAL Page Contents Woodstock Technical Support IntroductionMachine Description Left side view Controls and FeaturesB68=C HE886IDCH `gg`e`d\ej`fej Xikfe ZXlj\XdX\kfk\dXZ`e\ip% SAFETYJ8=KPSafety Additional Safety for Dust Collectors Full-Load Current Rating Circuit Requirements for 110V PrewiredElectrical Circuit RequirementsExtension Cords For 110V Connection PrewiredFor 220V Connection Must be Rewired Grounding RequirementsUnpacking SetupInventory Canister Inventory Figure Qty Hardware and Tool Bag Inventory Figure QtyMachine Placement To assemble the dust collector, do these steps AssemblySetup Vacuum tube installed Screw Collection lid installation Canister bag installed To test run the machine, do these steps Test RunCollection System System SetupTips for Optimum Performance Metal Duct Duct MaterialPlastic Duct Flexible DuctFlex-hose grounded to Machine Plastic Blast System GroundingGeneral Operation OperationsRemote control receiver Hour Intervals Back Remote Control OperationBlack ABS Plastic Blast Gates Aluminum Blast Gates Cyclone Dust Collector AccessoriesEmptying Drum MaintenanceNormal Filter Cleaning GeneralMajor Filter Cleaning ServiceTo reprogram the remote control, do these steps Remote Control Reprogramming@I&FDGFEEK8D8% Damaged Electrical Safety Instructions HL8C@=@CKI@@8E% Due to CKI@8CIHL@IDEKJ% You MustStop Wiring DiagramTo convert the Model W1823 to 220V, do these steps 220V ConversionMagnetic switch box Problem Possible Cause TroubleshootingOpen 1 or 2 more blast gates to different branch Parts Description Main Parts ListLabel Placement Model W1823 Mfg. Since 9/10 Place Stamp Here Warranty =\FjVainBVXcZhVcYIddah