8Field wiring

Low voltage connections

1.Route all low voltage wires through the knockouts in the rear of the boiler, as shown in FIG. 8-2.

2.Connect low voltage wiring to the low voltage connection board as shown in FIG. 8-3 on page 48 of this manual and the boiler wiring diagram.

Figure 8-2Routing Field Wiring

LOW VOLTAGE

CONNECTION BOARD

LINE VOLTAGE

JUNCTION BOX

LOW VOLTAGE

WIRING KNOCKOUTS

LINE VOLTAGE

WIRING KNOCKOUTS

Thermostat

1.Connect the room thermostat or end switch (isolated contact only) to terminals R and W, as shown in FIG. 8-3.

2.Install the thermostat on the inside wall away from influences of drafts, hot or cold water pipes, lighting fixtures, television, sunlight, or fireplaces.

3.Thermostat anticipator (if applicable):

a.If connected directly to boiler, set for 0.1 amps.

b.If connected to relays or other devices, set to match total electrical power requirements of connected devices. See device manufacturers’ specifications and thermostat instructions for details.

Outdoor temperature sensor

1.Connect the outdoor temperature sensor (FIG. 8-3) to the Outdoor Sensor terminals on the connection board to enable outdoor reset operation of the Knight XL. Do not install the outdoor sensor.

2.Mount the sensor on an exterior wall, shielded from direct sunlight or flow of heat or cooling from other sources.

3.Route sensor wires through a knockout at the rear of the boiler (see FIG. 8-2).

Installation & Operation Manual

DHW tank sensor

By installing a tank sensor, the SMART SYSTEM control can perform the tank thermostat function. The SMART SYSTEM control automatically detects the presence of this sensor, and generates a DHW call for heat when the tank temperature drops 6°F (3°C) below the tank set point, and finishes the call for heat when the tank temperature reaches the tank set point.

The tank sensor included with the Lochinvar Squire® indirect DHW tanks (TST2032) is the only sensor suitable for use with the SMART SYSTEM control. Connect the sensor leads to the DHW Tank Sensor (AUX) terminals on the low voltage connection board (FIG. 8-3). Consult the tank manufacturer for application and performance when used with any other indirect tank.

￿WARNING Failure to use the correct sensor may result in the tank temperature being either above

or below the set point. Failure to consult the manufacturer of the indirect tank, when the Squire is not used, may result in decreased performance or the risk of scald injury.

If TST2032 is not compatible with the indirect tank, a tank thermostat can be used to control the boiler. The tank thermostat should be installed per the manufacturer’s instructions and wired to the DHW Thermostat terminals on the low voltage connection board (FIG. 8-3).

Auxiliary device proving switch

1.When the operation of an auxiliary device needs to be verified before the boiler fires, remove the jumper wire from these terminals and connect them to the normally open contacts on its proving switch (FIG. 8-3).

High gas pressure switch

1.If a switch is provided to detect excessive gas pressure, remove the jumper wire from the terminals on the connection board, and then connect them to its normally closed contacts (FIG. 8-3).

Low gas pressure switch

1.If a switch is provided to detect low gas pressure, remove the jumper wire from the terminals on the connection board and connect them to its normally open contacts (FIG. 8-3).

2.If both a high and low gas pressure switch is used, connect their respective contacts in series, and connect them to the terminals on the connection board (FIG. 8-3).

DHW (Domestic Hot Water) thermostat

1.Connect the DHW tank thermostat to the Tank Thermostat terminals on the connection board (FIG. 8-3).

46

Flow switch

1.A flow switch is used to guarantee flow through the boiler before allowing it to fire. The flow switch must be installed in line with the boiler.

2.Remove the jumper wire from the terminals on the connection board and connect these terminals to the normally open contacts on the flow switch (FIG. 8-3).

Image 46 Contents
Models 399 Save this manual for future referenceContents When servicing boiler Please read before proceedingKnight XL How it works Air pressure switch Pump relay board ModelModels 600 Ratings Knight XL Boiler =B=R RatingDetermine boiler location Installation must comply withCloset and alcove installations Before locating the boiler, checkFor closet installations, Cpvc or TOPVent and air piping Residential garage installationProvide air openings to room Flooring and foundationProducts to avoid When using an existing vent system to install a new boilerAreas likely to have contaminants When removing a boiler from existing common vent system Model Prepare boilerRemove boiler from wood pallet Gas conversionsLeveling the boiler Models 600General venting Direct venting options Vertical Vent Installing vent or air piping Install vent and combustion air pipingRequirements for installation in Canada General ventingApproved Stainless Steel Vent Manufacturers PVC/CPVC air intake/vent connectionsMake Air inlet pipe materials Stainless steel ventFasNSeal Saf-T Vent Stainless steel air intake/vent connectionsOptional room air Removing from existing ventModel Description Kit Number Air contaminationVent/air termination sidewall If using the alternate sidewall terminationSidewall direct venting Determine location3AClearance to Gravity Air Inlets Prepare wall penetrations Bird Screen TypicalMultiple vent/air terminations Prepare wall penetrations Alternate Field Supplied OptionTermination and fittings Sidewall termination installation Description and usage9Concentric Vent Dimensional Drawing Models 399 11Concentric Vent Sidewall Attachment Multiventing sidewall terminationsVertical direct venting Vent/air termination verticalPrepare roof penetrations 2Vertical Terminations with Multiple BoilersVertical termination installation 4Concentric Vertical TerminationMultiventing vertical terminations Mm see -9,Hydronic piping Hydronic piping Near boiler piping connections Flow switch adjustmentCirculator sizing 20F 25F 30F 35F Head FeetPressure 399 500 600 700 800Near boiler piping components 7Single Boiler Primary/Secondary Piping Number of Units Model Manifold Pipe Sizes in Inches mm Connecting gas supply piping Gas connections Natural gas Propane GasIron Pipe Nominal Natural Gas Pipe Capacity ChartCheck inlet gas supply Length of Pipe in Straight FeetGas valve replacement Gas PressureInstallation must comply with Field wiringLine voltage connections High gas pressure switch Outdoor temperature sensorAuxiliary device proving switch Low gas pressure switchSystem supply sensor Alarm contactsWiring of the cascade Boiler management system3Low Voltage Field Wiring Connections Condensate disposal Condensate drainCheck/control water chemistry Freeze protection when usedStart-up Fill and test water systemInspect/fill condensate system Check for gas leaksCheck thermostat circuits Inspect/check condensate lines and fittingsIf boiler does not start correctly Final checks before starting the boilerStart the boiler Check system and boilerFor Your Safety Read Before Operating Set space heating operation Natural Gas PropaneConfiguration of the cascade Set domestic hot water DHW operationOperating information GeneralProtection features Outdoor reset operation, if used Boiler temperature regulationCascade DHW, Night Setback, and Ramp Delay operation with Cascade Sequence of the cascadeSequence of operation BLR IgnitionKnight XL control module ShutdownUser Access modesInstaller To save parameters and exit programmingSet Point Met ServiceStandby PrepurgeSYS ***.*F Control will display the actual fan motor RPMDelay 10V in **.VdcOperation of the cascade Service technician Maintenance Maintenance and annual startupOwner maintenance Clean condensate trap Check all piping for leaks MaintenanceAddress reported problems Inspect boiler areaCheck expansion tank Flue vent system and air pipingCheck water system Check boiler relief valveCheck control settings Check ignition ground wiringCheck all boiler wiring Inspect ignition and flame sense electrodesCleaning boiler heat exchanger Check flame signalReview with owner Diagrams High Voltage2Ladder Diagram Page