Harman VF3000 manual 20Maintenance, Ash Removal, Weekly, Every 3 months

Page 20

20Maintenance

Spring handle

Ash Removal

With each hopper of coal that is burned, approximately one ash pan full of ashes must be removed. Failure to re- move ashes will result in a blocked grate and the fire will not burn properly. Remember, the ash pan will be hot, so always wear protective gloves.

Ashes should be placed in a metal container with a tight fitting lid. The closed container of ashes should be placed on a non-combustible floor or on the ground, well away from all combustible materials, pending final disposal. If the ashes are disposed of by burial in soil, or otherwise locally dispersed, they should be retained in the closed container until all cinders have thoroughly cooled.

Weekly:

The small tray in the side of the stoker should be removed and emptied.

The spring handle located at the center of the unit should be cycled in and out several times. This action cleans the interior of the heat exchanger and causes the dust to fall into the ashpan.

Every 3 months:

The grate “clean-out” slide should be opened and reclosed as shown in drawings below.

In the “closed” position, be sure the “grate clean-out” plate slide is straight across as shown.

Baffle slideThe easiest way to handle this slide is through the ash door with a poker inserted into the hole at the end. The purpose of this operation is to let any ash build-up, under the grate, fall into the ash tub.

This operation can be performed while the unit is burn- ing. However, you should first lower the thermostat to lower the stove temperature and be sure you are wearing protective gloves.

Slide open

Slide closed

Image 20
Contents VF3000 Coal Stoker Boiler Page Contents Introduction Specifications/Hot Water Coil Hot Water CoilWarnings Never sleep in the same room with any coal burning stovePacking List Assembly Grate AssemblyFeeder 10Assembly Grates and FirebrickVenting11 Draft12Venting ChimneyVenting13 Do not connect to any air distribution duct or system14Installation Aquastat and WiringInstallation Basic Plumbing16Installation Clearances InstallationVerti-Flow Stoker Control Verti-FlowStoker ControlHow to operate the Stoker Control Verti-Flow Stoker ControlStarting a fire Feed AdjustmentOperation19 20Maintenance Ash RemovalWeekly Every 3 monthsMaintenance21 AnnuallyStoker Control Troubleshooting 22TroubleshootingFeeding Problems Aquastat Installation A350My350, s35024AQUASTAT Feeder Parts List Wiring Diagram & Fuel CoalVF3000 At har Warranty29 Harman Central Heating Products Limited Warranty30Notes