B. Installing Vent Components

The glass must be taken off again for positioning the logs when the unit is finally installed in place and finished around it. Re-install the glass door. Attach vent system to the top starting collars.

1.Attach the First Vent Component to the Starting Collars

To attach the first vent component to the starting collars of the fireplace:

Apply a 3/8 inch (9.5mm) bead of stove cement around the 5 inch (127mm) fireplace starting collar.

Make sure that the fireplace rope gasket supplied with the fireplace seals between the first 8-5/8 inch (219mm) vent component and the outer fireplace wrap.

Lock the vent components into place by sliding the con- centric pipe sections with four (4) equally spaced interior beads into the fireplace collar or previously installed com- ponent end with four (4) equally spaced indented sections.

When the internal beads of each 8-5/8 inch (219mm) outer pipe line up, rotate the pipe section clockwise about one-quarter (1/4) turn. The vent pipe is now locked together.

The first 90° elbow installed in the vent system of a rear venting fireplace MUST BE in a vertical position.

STARTING

COLLAR

STOVE

SEALANT

BEAD

FIRST VENT

COMPONENT

1 INCH (25.4mm)

Figure 10. Attaching the First Vent Component to the Starting Collars

!WARNING: A 3/8 INCH (9.5 MM) BEAD OF STOVE CEMENT MUST BE PLACED AROUND

THE 5 INCH (127 MM) FIREPLACE STARTING COL-

LAR BEFORE ATTACHING THE FIRST VENT COM- PONENT. FAILURE TO SEAL THIS JOINT MAY CAUSE THE FIREPLACE TO OPERATE IMPROPER- LY. SEE THE DIAGRAM .

!WARNING: ENSURE THAT THE FIBER- GLASS ROPE GASKET SUPPLIED WITH

THE FIREPLACE SEALS BETWEEN THE FIRST VENT COMPONENT AND THE OUTER FIREPLACE WRAP.

If the installation is for a termination cap attached directly to the fireplace, skip to the sections, Install Firestops and Vent Termination.

16

Image 12
Contents Installers Guide What to do if you smell gasSafety and Warning Information Table of Contents High Altitude Installations Installation CodesAppliance Certification CertificationPre-install Preparation Introducing the Heat-N-Glo Gas FireplacesANY Such Action MAY Possibly Cause a Fire Hazard Diagram of the 7000XLS and 6000XLSB Fireplace Dimensions, Locations Locating the FireplaceFraming the Fireplace Space Requirements Clearance Requirements32 156mm Installing the Vent System Identifying Vent ComponentsVent System Approvals Vent System Components and Termination KitsVenting with ONE 1 90 Elbow Venting with Three 3 90 Elbows Venting with three 90 elbowsInstalling Vent Components Attach the First Vent Component to the Starting CollarsTo Install the Heat Shield Install Support BracketsTo install support brackets for horizontal runs Continue Adding Vent Components12 Hole and Vent Pipe Ceiling Firestop Ceiling Side Attic FirestopVent Termination Pointing UP=VENT Terminal =AIR Supply Inlet Minimum for vinyl clad soffitsMinimum Height from Roof to Lowest Discharge Opening Positioning, Leveling, and Securing the Fireplace Gas Control SystemSecuring of a Fireplace Standing Pilot Ignition SystemGas Supply Line Gas Pressure RequirementsTo Check for GAS Leaks Wiring the Fireplace For Standing Pilot Ignition Wiring Appliance RequirementsOptional Accessories Remote Wall SwitchFinishing Hearth ExtensionsInstalling Trim, Logs, and Ember Material CeramicAfter the Installation Double-check for faulty componentsBefore Lighting the Fireplace Lighting the FireplaceFireplace Maintenance Important Turn OFF the GAS Before Servicing Your Fireplace