B. Constructing the Appliance Chase

A chase is a vertical box-like structure built to enclose the gas appliance and/or its vent system. In cooler climates the vent should be enclosed inside the chase.

NOTICE: Treatment of ceiling firestops and wall shield firestops and construction of the chase may vary with the type of building. These instructions are not substitutes for the requirements of local building codes. Therefore, you MUST check local building codes to determine the requirements to these steps.

Chases should be constructed in the manner of all out- side walls of the home to prevent cold air drafting prob- lems. The chase should not break the outside building envelope in any manner.

Walls, ceiling, base plate and cantilever floor of the chase should be insulated. Vapor and air infiltration barriers should be installed in the chase as per regional codes for the rest of the home. Additionally, in regions where cold air infiltration may be an issue, the inside surfaces may be sheetrocked and taped for maximum air tightness.

To further prevent drafts, the wall shield and ceiling fire- stops should be caulked with high temperature caulk to seal gaps. Gas line holes and other openings should be caulked with high temp caulk or stuffed with unfaced in- sulation. If the appliance is being installed on a cement slab, a layer of plywood may be placed underneath to prevent conducting cold up into the room.

C. Clearances

NOTICE: Install appliance on hard metal or wood surfaces extending full width and depth. DO NOT install directly on carpeting, vinyl, tile or any combustible material other than wood.

WARNING! Risk of Fire! Maintain specified air space clearances to appliance and vent pipe:

Insulation and other materials must be secured to prevent accidental contact.

The chase must be properly blocked to prevent blown insulation or other combustibles from entering and making contact with fireplace or chimney.

Failure to maintain airspace may cause overheating and a fire.

A

FROM TOP OF HOOD TO CEILING

E

B

F

J

 

 

H

 

K

 

 

 

C

 

 

 

 

 

 

 

 

 

D

 

 

 

 

 

 

G

 

 

 

 

 

 

 

 

 

 

 

 

 

I

 

 

 

 

 

* MINIMUM FRAMING DIMENSIONS

 

 

 

 

 

A

B

C

D

E

F

G

H

I

J

K

 

Rough

Rough

Rough

Rough

Clearance

 

Combustible

Behind

Sides of

Floor to Top

Front of

 

Opening

Opening

Opening

Opening

Combustible Floor

of Access

 

(Vent Pipe)

(Height)

(Depth)

(Width)

to Ceiling

 

Flooring

Appliance

Appliance

Panel

Appliance

 

 

 

 

 

 

 

Inches

10

44-3/4

22

42

31

0

0

1/2

1/2

4

36

mm

254

1137

559

1067

788

0

0

13

13

102

914

* Adjust framing dimensions for interior sheathing (such as sheetrock).

Figure 5.2 Clearances to Combustibles

Heat & Glo • 6000GCF-IPI, 6000GCF-IPILP2110-900 Rev. H • 11/08

19

Image 19
Contents HOT Surfaces What to do if you smell gasHomeowner Reference Information CongratulationsXxxxxxxx User Guide Table of ContentsReference Materials Appliance SetupTroubleshooting FinishingCONDITIONS, Exclusions & Limitation of Liability Limited Lifetime Warranty Listing and Code Approvals Requirements for the Commonwealth of Massachusetts Installation of Carbon Monoxide DetectorsOperating Instructions User Guide Gas Fireplace SafetyYour Fireplace Clear Space Fixed Glass AssemblyRemote Controls, Wall Controls and Wall Switches Fan Kit optionalGAS Valve Lighting Instructions IPIFinal inspection by What to do if YOU Smell GASIssue Solutions Frequently Asked QuestionsAfter Fireplace is Lit Remote Control Maintenance and ServiceMaintenance Tasks-Homeowner Glass CleaningLogs Maintenance Tasks-Qualified Service TechnicianGasket Seal and Glass Assembly Inspection VentingEither cobrahead or SIT Typical Appliance System Getting StartedTools and Supplies Needed Design and Installation ConsiderationsInspect Appliance and Components Selecting Appliance Location Framing and ClearancesConstructing the Appliance Chase Minimum Framing DimensionsClearances Combustible Mantels Mantel and Wall ProjectionsCombustible Mantel Legs or Wall Projections Vent Termination Minimum Clearances Termination Locations= Vent Terminal = AIR Supply Inlet = Area Where Terminal is not PermittedUse of Elbows Vent Information and DiagramsApproved Pipe Vent Table KeySLP series vent pipe, if desired Vent Diagrams Top Vent Horizontal TerminationTop Vent Horizontal Termination Three Elbows Break Here ChartH1 Maximum V1 + Minimum Top Vent Vertical Termination Two ElbowsPipe Clearances to Combustibles Vent Clearances and FramingHeat Shield Above First 900 Elbow Combustible Wall Penetration Wall Penetration FramingNon-Combustible Wall Penetration Pipe DVP Install the Ceiling FirestopFlat Ceiling Installation Install Attic Insulation ShieldVaulted Ceiling Installation Appliance Preparation Temporary Access PanelAttaching Sheetrock Ledges Securing and Leveling the Appliance Installing the Fiberglass GasketAssemble Pipe Sections Installing Vent PipeAttach Vent to the Firebox Assembly Assemble Vent SectionsSecure the Vent Sections Assemble Slip SectionsDisassemble Vent Sections 10 Rotate Seams for DisassemblyAssemble and Install Storm Collar Install Metal Roof FlashingApply Sealant TOP & Partial Sides Install RF4-8Heat Shield Requirements for Horizontal Termination Install Vertical Termination CapAnsi Z223.1 and CAN/CGA-B149 installation codes Install Horizontal Termination CapGas Connection Gas InformationFuel Conversion Gas PressureElectrical Information Wiring RequirementsIntellifire Ignition System Wiring Optional Accessories RequirementsIntellifire Pilot Ignition IPI Wiring Diagram Electrical Service and RepairWall Switch Installation for Fan Optional Junction Box InstallationFacing Material FinishingAppliance Setup Ember Placement Install the RefractoryEmber Material Log #1 SRV2103-107 Install the Log Assembly12 Front View Air Shutter Settings Install the MeshInstall Trim and/or Surround Air Shutter SettingSymptom Possible Cause Corrective Action TroubleshootingIntellifire Ignition System Ues to spark, and main Reference Materials Appliance Dimension DiagramDVP vent components Vent Components DiagramsDVP vent components DVP-TRAPNot for use on these models DVP-HSM-BDVP-HRC-SS DVP-HRC-ZC-SS Horizontal Termination CAP Service Parts Log Set AssemblyStocked Service Parts ListAt Depot 6000GCF-IPI Contact Information