E. Install Metal Roof Flashing

Note: Skip this section if using the RF4-8.

See minimum vent heights for various pitched roofs (Figure 10.14) to determine the length of pipe to extend through the roof.

Slide the roof flashing over the pipe sections extending through the roof as shown in Figure 10.15.

 

 

HORIZONTAL

 

 

OVERHANG

2 FT.

20 INCHES MIN.

VERTICAL

MIN.

 

 

WALL

 

LOWEST

 

 

 

DISCHARGE

 

 

OPENING

 

GAS DIRECT VENT

 

 

TERMINATION CAP

 

 

 

 

X

 

 

12

 

 

ROOF PITCH

 

 

IS X/ 12

 

H (MIN.) - MINIMUM HEIGHT FROM ROOF

 

TO LOWEST DISCHARGE OPENING

Roof Pitch

 

H (Min.) Ft.

Flat to 6/12........................................1.0*

Over 6/12 to 7/12............................1.25*

Over 7/12 to 8/12..............................1.5*

Over 8/12 to 9/12..............................2.0*

Over 9/12 to 10/12............................. 2.5

Over 10/12 to 11/12 ......................... 3.25

Over 11/12 to 12/12 ........................... 4.0

Over 12/12 to 14/12........................... 5.0

Over 14/12 to 16/12........................... 6.0

Over 16/12 to 18/12........................... 7.0

Over 18/12 to 20/12........................... 7.5

Over 20/12 to 21/12........................... 8.0

* 3 foot minimum in snow regions

Figure 10.14 Minimum Height From Roof To Lowest Discharge

Opening

 

 

NOTICE: Failure to properly caulk the roof flashing could cause water entry.

Caulk the gap between the roof flashing and the outside diameter of the pipe.

Caulk the perimeter of the flashing where it contacts the roof surface. See Figure 10.15.

CAULK

Figure 10.15

F. Assemble and Install Storm Collar

CAUTION! Risk of Cuts, Abrasions or Flying Debris. Wear protective gloves and safety glasses during instal- lation. Sheet metal edges are sharp.

Connect both halves of the storm collar with two screws (see Figure 10.16).

Wrap the storm collar around the exposed pipe section closest to the roof and align brackets. Insert a bolt (provided) through the brackets and tighten the nut to complete the storm collar assembly. Make sure the collar is tight against the pipe section.

Slide the assembled storm collar down the pipe section until it rests on the roof flashing (see Figure 10.17).

Caulk around the top of the storm collar (see Figure 10.23).

Figure 10.16 Assembling the Storm Collar

Figure 10.17 Assembling the Storm Collar Around the Pipe

Heat & Glo • 6000GCF-IPI, 6000GCF-IPILP2110-900 Rev. H • 11/08

37

Image 37
Contents HOT Surfaces What to do if you smell gasHomeowner Reference Information CongratulationsXxxxxxxx User Guide Table of ContentsTroubleshooting Appliance SetupFinishing Reference MaterialsCONDITIONS, Exclusions & Limitation of Liability Limited Lifetime Warranty Listing and Code Approvals Requirements for the Commonwealth of Massachusetts Installation of Carbon Monoxide DetectorsOperating Instructions User Guide Gas Fireplace SafetyYour Fireplace Remote Controls, Wall Controls and Wall Switches Fixed Glass AssemblyFan Kit optional Clear SpaceFinal inspection by Lighting Instructions IPIWhat to do if YOU Smell GAS GAS ValveIssue Solutions Frequently Asked QuestionsAfter Fireplace is Lit Maintenance Tasks-Homeowner Maintenance and ServiceGlass Cleaning Remote ControlGasket Seal and Glass Assembly Inspection Maintenance Tasks-Qualified Service TechnicianVenting LogsEither cobrahead or SIT Typical Appliance System Getting StartedTools and Supplies Needed Design and Installation ConsiderationsInspect Appliance and Components Selecting Appliance Location Framing and ClearancesConstructing the Appliance Chase Minimum Framing DimensionsClearances Combustible Mantels Mantel and Wall ProjectionsCombustible Mantel Legs or Wall Projections Vent Termination Minimum Clearances Termination Locations= Vent Terminal = AIR Supply Inlet = Area Where Terminal is not PermittedApproved Pipe Vent Information and DiagramsVent Table Key Use of ElbowsSLP series vent pipe, if desired Vent Diagrams Top Vent Horizontal TerminationTop Vent Horizontal Termination Three Elbows Break Here ChartH1 Maximum V1 + Minimum Top Vent Vertical Termination Two ElbowsPipe Clearances to Combustibles Vent Clearances and FramingHeat Shield Above First 900 Elbow Combustible Wall Penetration Wall Penetration FramingNon-Combustible Wall Penetration Pipe DVP Install the Ceiling FirestopFlat Ceiling Installation Install Attic Insulation ShieldVaulted Ceiling Installation Appliance Preparation Temporary Access PanelAttaching Sheetrock Ledges Securing and Leveling the Appliance Installing the Fiberglass GasketAttach Vent to the Firebox Assembly Installing Vent PipeAssemble Vent Sections Assemble Pipe SectionsSecure the Vent Sections Assemble Slip SectionsDisassemble Vent Sections 10 Rotate Seams for DisassemblyAssemble and Install Storm Collar Install Metal Roof FlashingApply Sealant TOP & Partial Sides Install RF4-8Heat Shield Requirements for Horizontal Termination Install Vertical Termination CapAnsi Z223.1 and CAN/CGA-B149 installation codes Install Horizontal Termination CapFuel Conversion Gas InformationGas Pressure Gas ConnectionIntellifire Ignition System Wiring Wiring RequirementsOptional Accessories Requirements Electrical InformationIntellifire Pilot Ignition IPI Wiring Diagram Electrical Service and RepairWall Switch Installation for Fan Optional Junction Box InstallationFacing Material FinishingAppliance Setup Ember Placement Install the RefractoryEmber Material Log #1 SRV2103-107 Install the Log Assembly12 Front View Install Trim and/or Surround Install the MeshAir Shutter Setting Air Shutter SettingsSymptom Possible Cause Corrective Action TroubleshootingIntellifire Ignition System Ues to spark, and main Reference Materials Appliance Dimension DiagramDVP vent components Vent Components DiagramsDVP vent components DVP-TRAPNot for use on these models DVP-HSM-BDVP-HRC-SS DVP-HRC-ZC-SS Horizontal Termination CAP Service Parts Log Set AssemblyStocked Service Parts ListAt Depot 6000GCF-IPI Contact Information