Hearth and Home Technologies 6000GCF-IPIL Installing Vent Pipe, Assemble Vent Sections

Page 34

10 Installing Vent Pipe

A. Assemble Vent Sections

Attach Vent to the Firebox Assembly

Note: The end of the pipe sections with the lanced tabs will face toward the appliance.

Attach the first pipe section to the starting collar:

Lanced pipe end to the starting collar

Inner pipe over inner collar

Push the pipe section until all lanced tabs snap in place

Lightly tug on pipe to confirm it has locked.

Commercial, Multi-family (Multi-level exceeding two sto- ries), or High-Rise Applications

All outer pipe joints must be sealed with high temperature silicone, including the slip section that connects directly to the horizontal termination cap.

Figure 10.1 High Temperature Silicone Sealant

Apply a bead of silicone sealant inside the female outer pipe joint prior to joining sections. See Figure 10.1

Only outer pipes need to be sealed. All unit collar, pipe, slip section, elbow and cap outer flues shall be sealed in this manner, unless otherwise stated.

WARNING! Risk of Fire or Explosion! DO NOT break silicone seals on slip sections. Use care when remov- ing termination cap from slip pipe. If slip section seals are broken during removal of the termination cap, vent may leak.

Assemble Pipe Sections

A

B

Figure 10.2

Lances

Figure 10.3

Per Figure 10.2:

Start the inner pipe on the lanced end of section A into the flared end of section B.

Start the outer pipe of section A over the outer pipe of section B.

Once both vents sections are started, push firmly until all lanced tabs lock into place.

Lightly tug on the pipe to confirm the tabs have locked.

It is acceptable to use screws no longer than 1/2 in. (13

mm)to hold outer pipe sections together. If predrilling holes, DO NOT penetrate inner pipe.

For 90º and 45º elbows that are changing the vent direction from horizontal to vertical, one screw minimum should be put in the outer flue at the horizontal elbow joint to prevent the elbow from rotating. Use screws no longer than 1/2 in. (13 mm). If predrilling screw holes, DO NOT penetrate inner pipe.

Note: Make sure that the seams are not aligned to prevent unintentional disconnection.

CORRECT

Figure 10.4 Seams

INCORRECT

34

Heat & Glo • 6000GCF-IPI, 6000GCF-IPILP2110-900 Rev. H • 11/08

Image 34
Contents What to do if you smell gas HOT SurfacesHomeowner Reference Information CongratulationsXxxxxxxx Table of Contents User GuideFinishing Appliance SetupTroubleshooting Reference MaterialsCONDITIONS, Exclusions & Limitation of Liability Limited Lifetime Warranty Listing and Code Approvals Installation of Carbon Monoxide Detectors Requirements for the Commonwealth of MassachusettsOperating Instructions User Guide Gas Fireplace SafetyYour Fireplace Fan Kit optional Fixed Glass AssemblyRemote Controls, Wall Controls and Wall Switches Clear SpaceWhat to do if YOU Smell GAS Lighting Instructions IPIFinal inspection by GAS ValveIssue Solutions Frequently Asked QuestionsAfter Fireplace is Lit Glass Cleaning Maintenance and ServiceMaintenance Tasks-Homeowner Remote ControlVenting Maintenance Tasks-Qualified Service TechnicianGasket Seal and Glass Assembly Inspection LogsEither cobrahead or SIT Getting Started Typical Appliance SystemTools and Supplies Needed Design and Installation ConsiderationsInspect Appliance and Components Framing and Clearances Selecting Appliance LocationConstructing the Appliance Chase Minimum Framing DimensionsClearances Combustible Mantels Mantel and Wall ProjectionsCombustible Mantel Legs or Wall Projections Termination Locations Vent Termination Minimum Clearances= Area Where Terminal is not Permitted = Vent Terminal = AIR Supply InletVent Table Key Vent Information and DiagramsApproved Pipe Use of ElbowsVent Diagrams Top Vent Horizontal Termination SLP series vent pipe, if desiredTop Vent Horizontal Termination Three Elbows Chart Break HereTop Vent Vertical Termination Two Elbows H1 Maximum V1 + MinimumPipe Clearances to Combustibles Vent Clearances and FramingHeat Shield Above First 900 Elbow Combustible Wall Penetration Wall Penetration FramingNon-Combustible Wall Penetration Install the Ceiling Firestop Pipe DVPFlat Ceiling Installation Install Attic Insulation ShieldVaulted Ceiling Installation Appliance Preparation Temporary Access PanelAttaching Sheetrock Ledges Installing the Fiberglass Gasket Securing and Leveling the ApplianceAssemble Vent Sections Installing Vent PipeAttach Vent to the Firebox Assembly Assemble Pipe SectionsAssemble Slip Sections Secure the Vent Sections10 Rotate Seams for Disassembly Disassemble Vent SectionsInstall Metal Roof Flashing Assemble and Install Storm CollarInstall RF4-8 Apply Sealant TOP & Partial SidesInstall Vertical Termination Cap Heat Shield Requirements for Horizontal TerminationInstall Horizontal Termination Cap Ansi Z223.1 and CAN/CGA-B149 installation codesGas Pressure Gas InformationFuel Conversion Gas ConnectionOptional Accessories Requirements Wiring RequirementsIntellifire Ignition System Wiring Electrical InformationElectrical Service and Repair Intellifire Pilot Ignition IPI Wiring DiagramJunction Box Installation Wall Switch Installation for Fan OptionalFinishing Facing MaterialAppliance Setup Ember Placement Install the RefractoryEmber Material Install the Log Assembly Log #1 SRV2103-10712 Front View Air Shutter Setting Install the MeshInstall Trim and/or Surround Air Shutter SettingsSymptom Possible Cause Corrective Action TroubleshootingIntellifire Ignition System Ues to spark, and main Appliance Dimension Diagram Reference MaterialsVent Components Diagrams DVP vent componentsDVP-TRAP DVP vent componentsDVP-HSM-B Not for use on these modelsDVP-HRC-SS DVP-HRC-ZC-SS Horizontal Termination CAP Log Set Assembly Service PartsStocked Service Parts ListAt Depot 6000GCF-IPI Contact Information