E. Vent Diagrams

 

 

 

 

Top Vent - Horizontal Termination

 

WARNING

 

 

 

 

Note: The 6000 series fireplaces can adapt to

Fire Risk.

Explosion Risk.

 

 

Do NOT pack insulation or other combustibles

SLP series vent pipe, if desired.

between ceiling firestops.

 

 

When venting off the top of the unit, use a DVP-2SL adapter and

• ALWAYS maintain specified clearances around

a minimum 48 inch vertical section of SLP series vent pipe.

venting and firestop systems.

 

After the 48 inch vertical section, the venting table rules

• Install wall shield and ceiling firestops as speci-

must be followed. The first 48 inch vertical section is NOT

fied.

 

 

 

Failure to keep insulation or other material away

counted as part of the vertical components in the table. It is

still counted as part of the overall maximum run. All venting

from vent pipe may cause fire.

 

 

 

 

 

table rules for the vent run must still be followed.

 

 

 

 

 

 

WARNING

 

Example: DVP pipe 3 ft. min. vertical = 11 ft. max. horizontal

Fire Risk.

 

 

 

SLP pipe 7 ft. min. vertical = 11 ft. max. horizontal

• When using DVP-HRC-SS and DVP-HRC-ZC-

 

SS termination caps on top vented fireplaces, a

 

6 inch minimum vertical vent section is required

Top Vent - Horizontal Termination

before installing first elbow.

 

 

 

 

 

One Elbow

V1 Minimum

H1

Maximum

6 inches

152 mm

3 ft.

914 mm

 

 

1 ft.

305 mm

3 ft.

914 mm

 

2 ft.

610 mm

6 ft.

1.8 m

 

3 ft.

914 mm

9 ft.

2.7 m

V1

4 ft.

1.2 m

12 ft.

3.7 m

H1

V1 + H1 = 40 ft. (12.2 m) Maximum

 

 

H1 = 20 ft. (6.1 m) Maximum

 

V1 = 6 inches (152 mm) Minimum

Figure 7.3

Two Elbows

H2

V1

H1

 

V1 Minimum

H1 + H2 Maximum

1 ft.

305 mm

Cannot do

1 1/2 ft.

457 mm

1-1/2 ft.

457 mm

2 ft.

610 mm

3 ft.

914 mm

 

 

 

 

3 ft.

914 mm

6 ft.

1.8 m

 

 

 

 

4 ft.

1.2 m

9 ft.

2.7 m

V1 + H1+ H2 = 50 ft. (15.2 m) Maximum

H1 + H2 = 17 ft. (5.2 m) Maximum

V1 = 1 ft. (305 mm) Minimum

 

INSTALLED

Figure 7.4

HORIZONTALLY

 

24

Heat & Glo • 6000GCF-IPI, 6000GCF-IPILP2110-900 Rev. H • 11/08

Image 24
Contents What to do if you smell gas HOT SurfacesCongratulations Homeowner Reference InformationXxxxxxxx Table of Contents User GuideAppliance Setup TroubleshootingFinishing Reference MaterialsCONDITIONS, Exclusions & Limitation of Liability Limited Lifetime Warranty Listing and Code Approvals Installation of Carbon Monoxide Detectors Requirements for the Commonwealth of MassachusettsGas Fireplace Safety Operating Instructions User GuideYour Fireplace Fixed Glass Assembly Remote Controls, Wall Controls and Wall SwitchesFan Kit optional Clear SpaceLighting Instructions IPI Final inspection byWhat to do if YOU Smell GAS GAS ValveFrequently Asked Questions Issue SolutionsAfter Fireplace is Lit Maintenance and Service Maintenance Tasks-HomeownerGlass Cleaning Remote ControlMaintenance Tasks-Qualified Service Technician Gasket Seal and Glass Assembly InspectionVenting LogsEither cobrahead or SIT Getting Started Typical Appliance SystemDesign and Installation Considerations Tools and Supplies NeededInspect Appliance and Components Framing and Clearances Selecting Appliance LocationMinimum Framing Dimensions Constructing the Appliance ChaseClearances Mantel and Wall Projections Combustible MantelsCombustible Mantel Legs or Wall Projections Termination Locations Vent Termination Minimum Clearances= Area Where Terminal is not Permitted = Vent Terminal = AIR Supply InletVent Information and Diagrams Approved PipeVent Table Key Use of ElbowsVent Diagrams Top Vent Horizontal Termination SLP series vent pipe, if desiredTop Vent Horizontal Termination Three Elbows Chart Break HereTop Vent Vertical Termination Two Elbows H1 Maximum V1 + MinimumVent Clearances and Framing Pipe Clearances to CombustiblesHeat Shield Above First 900 Elbow Wall Penetration Framing Combustible Wall PenetrationNon-Combustible Wall Penetration Install the Ceiling Firestop Pipe DVPInstall Attic Insulation Shield Flat Ceiling InstallationVaulted Ceiling Installation Temporary Access Panel Appliance PreparationAttaching Sheetrock Ledges Installing the Fiberglass Gasket Securing and Leveling the ApplianceInstalling Vent Pipe Attach Vent to the Firebox AssemblyAssemble Vent Sections Assemble Pipe SectionsAssemble Slip Sections Secure the Vent Sections10 Rotate Seams for Disassembly Disassemble Vent SectionsInstall Metal Roof Flashing Assemble and Install Storm CollarInstall RF4-8 Apply Sealant TOP & Partial SidesInstall Vertical Termination Cap Heat Shield Requirements for Horizontal TerminationInstall Horizontal Termination Cap Ansi Z223.1 and CAN/CGA-B149 installation codesGas Information Fuel ConversionGas Pressure Gas ConnectionWiring Requirements Intellifire Ignition System WiringOptional Accessories Requirements Electrical InformationElectrical Service and Repair Intellifire Pilot Ignition IPI Wiring DiagramJunction Box Installation Wall Switch Installation for Fan OptionalFinishing Facing MaterialAppliance Setup Install the Refractory Ember PlacementEmber Material Install the Log Assembly Log #1 SRV2103-10712 Front View Install the Mesh Install Trim and/or SurroundAir Shutter Setting Air Shutter SettingsTroubleshooting Symptom Possible Cause Corrective ActionIntellifire Ignition System Ues to spark, and main Appliance Dimension Diagram Reference MaterialsVent Components Diagrams DVP vent componentsDVP-TRAP DVP vent componentsDVP-HSM-B Not for use on these modelsDVP-HRC-SS DVP-HRC-ZC-SS Horizontal Termination CAP Log Set Assembly Service PartsService Parts List StockedAt Depot 6000GCF-IPI Contact Information