Baxi Potterton Condensing Combination Boiler manual Setting the Gas Valve

Page 48

x 2

Central Heating

 

Domestic Hot Water

Temperature Control

Fig. 102

Temperature Control

Selector Switch

Display

 

 

 

Reset

 

 

 

2

 

 

1

 

 

 

 

3

 

 

 

0

4

 

 

 

 

bar

 

Central Heating

Domestic Hot Water

Temperature Control

Temperature Control

Fig. 103

Fig. 104

Fig. 105

Fig. 106

Fig. 107

Flue Adaptor Test

15.0Setting the Gas Valve

15.1Setting the Gas Valve (CO2 check)

IMPORTANT: The CO2 must be only be checked and adjusted to set the valve if a suitable calibrated combustion analyser is available, operated by a competent person - see Section 13.1

1.

The combustion (CO2) may be checked after running the

boiler for several minutes. To do this it is necessary to set

the boiler to ‘Calibration Mode’.

2.

Ensure that all external controls are calling for heat. The

actual current boiler temperature is shown on the display.

3.

Turn both control knobs fully anticlockwise, then quickly

turn the right hand knob 1/4 clockwise twice and back fully

anticlockwise (Fig. 102).

4.

The display will now alternate between ‘SF’ and the

current boiler temperature and both green LEDs will flash

(Figs. 103 & 104).

5.

Turn the left hand knob fully clockwise. As the knob is

turned the display will change, indicating the fan speed.

6.

The display will show ‘00’, indicating maximum rate, then

revert to ‘P ‘ alternating with the current boiler temperature

(Figs. 105, 106 & 107).

7.

Remove the plug from the flue sampling test point. Insert

the analyser probe and allow sufficient time for the reading

to settle (Fig. 108).

 

The CO2 should be 8.7% ± 0.2

Plug

Point

8. It is possible to alter the CO2 by adjustment of the gas

valve. Remove the plastic cover from the Throttle

Adjustment Screw. At maximum rate the Throttle

Analyser Probe

Fig. 108

Offset

 

Adjustment Screw

Throttle

(cap fitted)

Adjustment Screw

 

 

(cover removed)

Adjustment Screw should be turned, using a suitable

hexagon key, until the correct reading is obtained (Fig. 109).

Turning clockwise will reduce the CO2. Anticlockwise will

increase the CO2.

9. The CO2 must then be checked at minimum rate. Turn

the left hand knob fully anti-clockwise. As the knob is turned

the display will change, indicating the fan speed. When the

display reads ‘ 0’ the boiler runs at minimum rate.

The CO2 should be 8.4% ± 0.2

10. With the boiler on minimum, the Offset Adjustment

Screw must be altered, using a suitable hexagon key, after

Reduce CO2

Increase CO2

at min. rate

at min. rate

If the CO2 is reset at minimum rate it must be rechecked at maximum rate again and adjusted if required. If the CO2 is reset at maximum rate it must be rechecked at minimum rate and adjusted if required.

 

Reduce CO2

Increase CO2

 

at max. rate

at max. rate

Gas Valve

Fig. 109

 

Do not turn the adjustment screws more than 1/8 of a turn at a time. Allow the analyser reading to settle before any further adjustment

removing the cap (Fig. 109). Turning anti-clockwise will

reduce the CO2. Clockwise will increase the CO2.

11. The ‘Calibration Function’ is maintained for 20 minutes

unless the maximum CH temperature is exceeded. The

function can be disabled at any time by turning the right

hand knob.

12. Check the Combustion Performance (CO/CO2 ratio).

This must be less than 0.004.

48© Baxi Heating UK Ltd 2012

Image 48
Contents Installation & Service Instructions 0086 Installer Notification Guidelines Scheme Members onlyImportant Installation, Commissioning, Service & Repair LegislationCodes of Practice refer to the most recent version Safe Manual Handling GeneralPreparation TechniqueContents Contents of Pack IntroductionDescription Optional ExtrasGeneral Layout LayoutCentral Heating Mode Fig Domestic Hot Water Mode FigFrost Protection Mode Appliance OperationTechnical Data Heatmax Combi 24, 28Dimensions and Fixings System Details InformationCentral Heating Circuit BypassSafety Pressure Relief Valve Fig System Filling and PressurisingExpansion Vessel Central Heating only Domestic Hot Water Circuit Fig ShowersHard Water Areas Site Requirements LocationClearances Figs Site Requirement Ventilation of CompartmentsGas Supply Electrical SupplyCondensate Drain 50mm per 500mm minRun Minimum fallPlume Displacement Kit FlueBelow windows or openings on pitched roofs 2000 Likely flue positions requiring a flue terminal guardFlue Options Horizontal FluesHorizontal Flue Systems This bend is equivalent to 1 metreVertical Flues Vertical Flue SystemsRoof Terminal This bend is equivalent to 1 metre Metre for each 91.5 bend Metre for each 135 bendFlue Accessories Key Accessory Size Code NoFlue Dimensions For Roof TerminalsFlue Trim Terminal Guard FigPlume Displacement Plume Displacement Kit Fig28/33 Determining Permissible LengthsExample 5121368General Fitting Notes 30mmElbow to allow the flue to be installed as shown 60Ø extension piece. It must be secured using twoUsing a suitable bit e.g mm, drill through Extension and outlet. Secure using two of the screwsInstallation Unpacking & Initial PreparationFlushing After considering the site requirementsFitting The Boiler Condensate Drain see sectionFitting The Flue Wall Thickness Flue ElbowEnsure Elbow is fully engaged into Boiler Adaptor WasteY FlueInner Flue Support Bracket 25mm Extension Cut EndEnsure Extension is fully engaged into Boiler Adaptor Making The Electrical Connections Preliminary Electrical ChecksTerminal Block Cover Cable Clamp Commissioning Commissioning the BoilerSelector Switch Display Check the Operational Working Gas Inlet PressureGas Valve Completion CompletionCase Front Panel Facia Panel Servicing Annual ServicingAnnual Servicing Inspection Fan, Collector and Cover Assembly Threaded Bush Electrode Leads Venturi InjectorRestricter Filter Hall Effect Sensor Changing Components Igniter FigSpark and Sensing Electrodes Fig Fan Fig Venturi FigInjector Fig Gasket Venturi Injector Cover Gas Inlet Pipe Fan CollectorBurner Fig Insulation FigCentral Heating Temperature Sensor NTC Fig Safety Thermostat FigDHW Temperature Sensor NTC Fig Flue/Heat Exchanger Thermostat Sensor FigPump Head Only Fig Pump Complete FigAutomatic Air Vent Fig Pressure Gauge Figs Hall Effect Sensor FigDiverter Valve Motor Unit & Assembly Fig Plate Heat Exchanger FigSelector Switch Fig 14.22 P.C.B. FigGas Valve Fig Expansion Vessel FigSetting the Gas Valve Setting the Gas Valve CO2 checkIllustrated Wiring Diagram ElectricalShort Parts List Short Parts List306 302Fault Finding Initial Fault Finding ChecksError Codes Error 133 flashing Go to section ‘A’ Turn the selector switch toReset position for 5 seconds Pump runsError 133 flashing Go to section ‘I’ Turn Domestic Hot WaterOpen DHW tap fully Close DHW tapPCB X3 connector terminals 3 Switch terminalFan jammed or faulty winding Replace PCB Replace waterReplace sensor or PCB E28 Gas at burnerReplace gas valve Terminals 1Replace safety thermostat Replace PCB Is there 230V atReplace sensor Page GAS Boiler System Commissioning Checklist Service Record Brooks House, Coventry Road, Warwick. CV34 4LL

Condensing Combination Boiler specifications

The Baxi Potterton Condensing Combination Boiler is a sophisticated heating solution designed to meet the demands of modern households while promoting energy efficiency. This state-of-the-art boiler combines both heating and hot water capabilities into a compact unit, making it an ideal choice for homes with limited space.

One of the standout features of the Baxi Potterton Condensing Combination Boiler is its impressive energy efficiency. With a high energy efficiency rating, these boilers can significantly reduce energy bills and minimize carbon footprints. The condensing technology maximizes heat recovery, allowing the boiler to utilize heat that would otherwise be lost in traditional systems. By extracting more energy from the combustion process, homeowners can enjoy reliable heating and hot water without the typical energy waste associated with older boilers.

The Baxi Potterton range is engineered for easy installation and maintenance, featuring a lightweight design that simplifies the fitting process. The built-in digital control system allows homeowners to easily adjust settings for optimal comfort and energy usage. Additionally, the boiler includes a frost protection feature, making it a reliable option for homes in colder climates.

Another key characteristic of the Baxi Potterton Condensing Combination Boiler is its powerful hot water delivery system. The combination boiler provides instant hot water on demand, eliminating the need for a separate water tank. This ensures that households have a constant supply of hot water for showers, cooking, and other domestic needs, without long wait times.

Safety is a top priority with the Baxi Potterton. The boiler is equipped with multiple safety features, including pressure relief valves and safety cut-off systems, ensuring peace of mind for homeowners. The compact design further includes a quiet operation feature, which is particularly beneficial for households where noise levels need to be kept to a minimum.

In summary, the Baxi Potterton Condensing Combination Boiler is a highly efficient, compact, and user-friendly solution for home heating and hot water needs. With its advanced technology and strong emphasis on safety, it stands out as a reliable choice for modern households looking to improve energy efficiency while maintaining comfort. Whether you are replacing an old boiler or installing a new system, the Baxi Potterton offers a perfect blend of practicality and innovation.