Connection of piping

1.Move the indoor tubing and drain hose to the hole

Remove tubing holder and pull the tubing out of the chassis.

2.Replace the tubing holder into original position

3.Route the tubing and the drain hose staight backwards.

4.Insert the connecting cable into the indoor unit through the hole.

Do not connect the cable to the indoor unit

Make a small loop with the cable for easy connection later.

5.Tape the tubing and the connecting cable.

6.Indoor unit installation.

7.Connecting the pipings to the indoor unit.

PIPE SIZE

TORQUE

1/4"

1.8~2.5 kgf·m

3/8"

3.4~4.2 kgf·m

1/2"

5.5~6.6 kgf·m

5/8"

6.3~8.2 kgf·m

3/4"

9.9~12.1 kgf·m

Align the center of the pipings and suffciently tighten the flare nut with fingers.

Finally, tighten the flare nut with troque wrench until the wrench clicks.

When tightening the flare nut with troque wrench, ensure the direction for tightening follows the arrow on the wrench.

Indoor unit tubing

Flare nut

Pipings

Spanner

Torque wrench

Precautions inbending

1.If it is necessary to bend or stretch the tubing, use the spring which is attached to the tubing in stead of pipe bender.

Please make a careful notice to make a smooth line.

Hold the tubing with your two hands closely and then bend or stretch it slowly not to make any crack.

Remember that the radius (R) should not exceed 70mm (Refer to Fig. 1)

2.Do not repeat the bending process to prevent the tubing from cracking or crushing.

3.Keep in mind that the bending part should not be cracked and make the radius (R) as long as possible (Refer to Fig. 2)

Spring

R70mm

(Fig. 1)

R

(Fig. 2)

Installation Manual 13

Image 13
Contents LG Floor Standing Type Air Conditioner Table of Contents Use the correctly rated breaker or fuse Always ground the productOperation Be sure the installation area does not deteriorate with ageUse two or more people to lift and transport the product Keep level even when installing the productSelection of the best location Installation of UnitPiping length and the elevation Outdoor unit Installation Indoor Unit InstallationRefrigerant amount Selecting the locationOutdoor Unit Installation guide at the seasideInstallation works Descriptions Installation MethodInstallation Parts, Tools Use Preparation of installation parts and toolsCut the pipes and the cable Preparation of PipingConnection of piping Precautions in bendingMove the indoor tubing and drain hose to the hole Connecting the Cable to Indoor Unit Connecting the cables to the outdoor unit Connecting pipings to the outdoor unitPower supply Power Supply and WiringVacuum Drying of the Connecting Pipes and the Indoor Unit Form the Piping Final Check and Test Run Memo Floor Standing type Air Conditioner