Andrew ES73 manual Polarization at 45 degrees from Optimum Setting

Page 56

Step 7

Step 8

Step 9

Move the antenna in azimuth to obtain a null, then move ± in elevation to obtain a large peak signal. If not, move the antenna in the opposite azimuth direction through the peak and again move ± in elevation to obtain a large peak signal. If a larger peak is not found, you were on the main lobe.

NOTE: The following explanation for polarization adjustment addresses the special case of full transponder signals. Some applications may include partial transponder signals.

If your antenna is equipped with a linear polarizer, the antenna is aligned in azimuth and elevation (signal maximized) and 24 transponder signals (12 horizontal and 12 vertical) are noted, the polarization adjustment is set incorrectly and must be modified. If 12 transponder signals are noted, they may or may not be the properly polarized signals. Therefore 24 transponder signals must be visually noted in order to determine the prop- er polarization setting.

Rotate the feed assembly clockwise until 24 transponder signals are noted and of approximately equal amplitude.

NOTE: It is more accurate and visually easier to minimize the alternate set of transpon- der signals rather than maximizing the transponder of interest.

Figure 4-3: Polarization at 45 degrees from Optimum Setting

56

Operation

Image 56
Contents Meter ESA Table of Contents Meter Earth Station Antenna IntroductionProprietary Data Information and Assistance Technical Call From Call To Telephone FaxOverview Content How to Use This ManualOverview Getting StartedRecommended Tools Tool Size QuantityGetting Started Returning Equipment Step Installation Procedures Overview Foundation PreparationTensioning Step 1b A-325 Tensioning For bolts over four diametersTripod Ground Mount Assembly Azimuth Beam Step Support Legs Assembly Step 201315 Supports Step Panning Frame Assembly Step Step 201316 Supports 201487 201488 Panning Frame Outrigger Plate Support 201488 Outrigger Plate Step 301772 Tripod Tube Weldment 300026 Tripod Channel Legs Elevation Jackscrew Assembly Step 301771/301736 Elevation Jackscrew Azimuth Jackscrew Assembly Step Mount Assembly Step 201327A 201313A Step 221345 X 2-1/4 57 mm Upper Lower Collars Installation Procedures Step Horn Assembly Shown for Step 201065A Waveguide Support Equipment Enclosure Step Reflector Backstructure Assembly Step Step Center portion Andrew Flash logo Step Step Step Step Quadrapod Subreflector Strut Assembly Step Installation Procedures Step Step Reflector to Ground Mount Assembly Step Installation Procedures Subreflector Assembly Adjustment Step Step Cross-Axis Grounding Kit Step Step Overview Acquiring a Satellite OperationStep Polarization at 45 degrees from Optimum Setting Maximizing Odd Transponders Subreflector Adjustment Overview General Cleaning Electrical Parts Preventive MaintenancePreventive Maintenance Antenna Preventive Maintenance Drive System Voltage Current Checks Step Step Preventive Maintenance Jackscrews/Motors Gear Motor/Housing Fill Drain Requirements Lubrication Chart High-Speed Antenna Lubrication Points Medium-Speed Antenna Lubrication Points