Andrew ES73 manual Step

Page 42

Step 9

Step 10

Step 11

Step 12

Step 13

Step 14

Prior to installing panels 15 and 16 station a man on top of the drum assembly enclo- sure to install panel seam hardware. Care must be taken not to apply heavy weight to surface of panel segments.

Note that there are 16 panel segments each with 21 bolt holes numbered 1-21 from the center out which form concentric rings around the inside of the reflector as shown in Figure 53. Beginning with the center flash panel (segment 1) tighten all panel seam hardware corresponding to bolt hole ring 11, located above reflector tee segment/back strut assembly connection. Continue tightening ring 11 reflector seam hardware working counterclockwise.

Figure 53

Tighten panel seam hardware along rings 10 and 12 simultaneously beginning with panel seam 1.

Tighten panel seam hardware along rings 9 and 13 simultaneously beginning with panel seam 1.

Tighten panel seam hardware along rings in pairs simultaneously beginning with rings 14 and 15 working toward the outside of the reflector to seam hardware ring 21.

Tighten panel seam hardware along rings in pairs simultaneously beginning with hard- ware rings 7 and 8 working toward the inside of the reflector down to seam hardware ring 1.

42

Installation Procedures

Image 42
Contents Meter ESA Table of Contents Meter Earth Station Antenna IntroductionProprietary Data Information and Assistance Technical Call From Call To Telephone FaxOverview Content How to Use This ManualOverview Getting StartedRecommended Tools Tool Size QuantityGetting Started Returning Equipment Step Installation Procedures Overview Foundation PreparationTensioning Step 1b A-325 Tensioning For bolts over four diametersTripod Ground Mount Assembly Azimuth Beam Step Support Legs Assembly Step 201315 Supports Step Panning Frame Assembly Step Step 201316 Supports 201487 201488 Panning Frame Outrigger Plate Support 201488 Outrigger Plate Step 301772 Tripod Tube Weldment 300026 Tripod Channel Legs Elevation Jackscrew Assembly Step 301771/301736 Elevation Jackscrew Azimuth Jackscrew Assembly Step Mount Assembly Step 201327A 201313A Step 221345 X 2-1/4 57 mm Upper Lower Collars Installation Procedures Step Horn Assembly Shown for Step 201065A Waveguide Support Equipment Enclosure Step Reflector Backstructure Assembly Step Step Center portion Andrew Flash logo Step Step Step Step Quadrapod Subreflector Strut Assembly Step Installation Procedures Step Step Reflector to Ground Mount Assembly Step Installation Procedures Subreflector Assembly Adjustment Step Step Cross-Axis Grounding Kit Step Step Overview Acquiring a Satellite OperationStep Polarization at 45 degrees from Optimum Setting Maximizing Odd Transponders Subreflector Adjustment Overview General Cleaning Electrical Parts Preventive MaintenancePreventive Maintenance Antenna Preventive Maintenance Drive System Voltage Current Checks Step Step Preventive Maintenance Jackscrews/Motors Gear Motor/Housing Fill Drain Requirements Lubrication Chart High-Speed Antenna Lubrication Points Medium-Speed Antenna Lubrication Points