Cecilware BC301-IT, BC2-IT, BC302-IT specifications Installation and Operating Instructions

Page 4

INSTALLATION AND OPERATING INSTRUCTIONS

Warranty is void if the Brewer is connected to any Voltage other than the Voltage specified on the data label of the Brewer.

UNPACKING AND INSPECTION

Carefully unpack the Brewer by cutting the straps and lifting the carton off the Brewer.

ASSEMBLY AND SET-UP

The Brewer is shipped complete with:

DESCRIPTION

BC1-301-IT

BC2-IT, 302-IT

Adjustable legs

4

4

Carriers complete with Faucets and Covers

1

2

Funnels with sample Filter pack

1

2

Remove carriers from Brewer, one has the four (4) legs packed inside. Install legs by tilting Brewer on its back and screwing the legs into the threaded leg supports on bottom.

WATER HOOK UP

The National Sanitation Foundation (NSF) requires the following for NSF approved installation:

1.A quick disconnect water connection or enough extra coiled tubing (at least 2x the depth of the unit) so that the Brewer can be moved for cleaning underneath.

2.An approved flow-back prevention device such as a double check valve to be installed between Brewer and water supply.

WATER CONNECTION

The Brewer comes equipped with a ¼ inch compression water inlet fitting located in the back. Use a ¼ inch copper tubing to connect the Brewer to a cold water supply. Water pressure should be: 20 PSI min. to 90 PSI max. An external shut-off valve and a water filtering system with a charcoal filter are highly recommended.

Turn water supply on and check for leaks at the water inlet connections, tighten compression fitting if necessary.

ELECTRICAL CONNECTIONS

A terminal block inside the base compartment is provided for electrical connections. Opening for field conduit connections are provided in the bottom and the back of the base.

To access the Terminal Block, loosen the 2 screws on the side of the base cover. Disengage base cover from rear panel by lifting base cover up and lifting back towards rear panel.

Power Cord CE202 - Optional

 

RECOMMENDED WIRING SIZES

 

Model No.

Single (1) Phase

BC301-IT

12 AWG

BC2-IT, BC302-IT

10 AWG

Note:

1.Neutral (N) and Ground Wires to be 14 AWG Minimum.

2.Field wiring must be suitable for 75º C.

3.Use Copper wire only for all power supply connections.

4

Image 4
Contents Models BC2-ITSingle TwinMechanical Specifications Specifications Electrical SpecificationsSTART-UP Procedure Page Installation and Operating Instructions Programming Instructions To Change Or Reset Parameter ValuesModes of Operation Overview Modes of Operation Descriptions Brewing State Brew Fill Constant Calibration StateDilution Fill Constant Calibration State WarmersService Mode Dilution Delay ### Seconds Water TemperatureInfusion Time ## Seconds Soak Time ## SecondsLockout Temperature Sleep Timer ON/OFFWarmer Power Warmer Timer ON/OFFWeekend Timer ON/OFF Clock Setup ON/OFFAdjust Seconds DAY HHMM## Adjust Minutes DAY HH##SSError Mode Parts Identification BC2-IT, BC302-IT Back ViewTOP Cabin Parts Identification Elbow TubeQTY BC2-IT Description To prepare a sanitizing solution Front View BC301-ITTroubleshooting Guide Problem Probable Cause RemedySpecial Components Test and Adjustments Power Safety Relay Test Located inside top cabinTo Adjust Water Flow Rate Cecilware Corporation 120/240V