(2)Please keep the pliers, pipe cutting unit and Hansen valve clean, and keep them away from grease dirt.
12.5.3 Procedure for filling equipment
(1) Preparation before use
①Visually inspect recovery machine for abnormalities, etc.
②Keep all valves closed to equipment until really to proceed.
(2) Evacuation
①Connect recovery machine hoses to system fittings
②Switch on power.
③Switch on motor.
④Open all related valves.
⑤Observe the pointer of vacuum meter when it is accessing the mark
⑥Evacuation time shall not be less than 45 min.
⑦After evacuation close valves.
MAINTENANCE SERVICE AND TROUBLE SHOOTING
Maintenance Service and Trouble Shooting
⑧Switch off motor.
38