ADJUSTMENT OF THE OVEN BURNER MINIMUM

 

(LEFT and RIGHT OVEN)

G

This needs to be done only for the oven burner (the broil is a fixed capacity) by acting

 

on the thermostat in the following way:

 

– Turn on the burner by setting the thermostat knob on position .

 

– Remove the knob and unscrew the by-pass screw "G" (fig. 2.13) about three times

 

by passing a small flat screwdriver (Ø 3 mm blade, 100 mm length) through the panel

 

opening.

 

 

Re-mount the knob and let the oven heat up for about 10 minutes, then bring the knob

 

to position

(minimum) to operate the thermostat by-pass.

 

– After having removed the knob again and being very careful not to turn the tap rod,

Fig. 2.13

slowly screw the by-pass screws “G” (fig. 2.13) until you obtain a flame of 3-4 mm

 

in height.

 

 

N.B. For LP/PROPANE gas the by-pass screw must be fixed thoroughly.

After regulation repeat the operations indicated in paragraph “2. Pressure regulator” at pages 13 and 18.

If the range has been disconnected and then connected again to the gas supply line repeat the operations indicated in paragraph “5. Leak Testing” at page 18.

IMPORTANT:

After conversion to LP/PROPANE gas has been carried out affix inside the drawer, near the data plate, the conversion label supplied and also affix a conversion label at page 3 of this instruction manual.

23

Image 23
Contents Double Oven GAS Range ALL Ranges can TIP DATA PLATE Conversion Label Installation Instructions Electrical Grounding Instructions Replacement PartsProximity to Side Cabinets  installationGAS and Electric Connection Oven 305 Moving the Cooker Fitting the Adjustable FeetLevelling the Cooker Backguard or the island trim It is mandatory to installASSEMBLING THE BACKGUARD OR THE ISLAND TRIM28 15/16 735 mm Pressure Regulator Manual Shut-off Valve .1Explosion Hazard Lock Pressure Regulator InstallationImportant use two spanners to tighten the connection Page Range Manifold Manifold male Pipe fitting Rigid Pipe Connections Leak TestingFlexible Connections CONVERSION TO LP/PROPANE GAS SETTING THE PRESSURE REGULATOR .5INJECTORS TABLE Operations to be Performed When Substituting InjectorsSemirapid and triple ring burners Setting the Burner MinimumOven Burner LEFT and RIGHT OVEN Adjustment of the Oven Burner MinimumRecommended ground method Electrical connectionWiring Diagram Page Page Cod ß1