You can switch fuel sources (from gasoline to LP/NG, or from LP/NG to gasoline) while the generator is running. Follow the instructions below:

1. Disconnect all loads to the generator. Leave the engine running.

2. Turn the gasoline line shut-off valve to ON position.

3. Flip the fuel selector switch to the GASOLINE position.

1. Disconnect all loads to the generator. Leave the engine running.

2. Make sure LP or NG fuel is properly connected to ¾” NPT supply inlet and is being supplied.

WARNING:

If you smell gas, turn off engine and shut off gas supply immediately. Exit area and call gas supplier or fire department.

3.Flip the fuel selector switch to the NONE position. The fuel conversion should take 1-2 seconds.

4.Wait for the engine to begin sputtering. This indicates the engine is being starved of gasoline.

5.Flip the fuel selector switch to the LP/NG position.

6.Turn the gasoline line shut shut-off valve to OFF position.

7. Stopping

Stop the engine using the following steps:

1.Disconnect all loads to the generator.

2.Turn engine key switch to OFF position.

3.Turn gasoline line shut-off valve to OFF position.

4.The fuel lock-off solenoid automatically stops the flow of LP or NG to the engine.

5.Remove key from starter to prevent accidental starting of engine.

34

Image 34
Contents M165939J Hazard Signal Word Definitions Table of Contents About Your Generator About Your GeneratorAbout Your Generator cont’d Read this ManualSpecifications Specifications Item #165939JSafety Label Locations Item #165939J Part numbers DescriptionMachine Component Identification Item #165939J DescriptionReference Guide Reference 13 120V, 20A, Duplex Power Load Planning & Management Example conversion to wattsPower Load Planning & Management cont’d Total 6275WPlanning the Power Load Installation / Initial Set-UpUnpacking & Delivery Inspection Gas Hook-up Installation for Natural Gas or LPG if needed Installation / Initial Set-Up Set-up either as a Building BACK-UP or Portable Power Source Generator Current/Power Maximum Extension Cord Length Select a Suitable Site Structure allow at least a 7’ clearance Grounding the generator Battery Installation General safety rules for operation OperationOperation cont’d Operation cont’d Preparing for Operation ManualOperation cont’d Start LPG/NG supply If using Natural GasOperation cont’d Using LP/NG To start engine using LP or Natural Gas Starting the EngineTo start engine using gasoline Checking Generator Output Connecting Loads Stop the engine using the following steps Switching Fuels during operationStopping When you are finished using the generator, you must Storage & ExerciseOperation cont’d Maintenance & Repair Maintenance & RepairMaintenance & Repair cont’d Troubleshooting TroubleshootingBattery Safety Summary of Importation Information for OperationInstallation / Initial Set-up Safety Summary of Importation Information for Operation cont’dPropane & Natural Gas Safety Know how to operate\Gasoline Safety Personal protective equipmentSafety During Use Safety After use Generator Exploded View Rev J Fig # Description Qty Wiring Diagram Rev J Diag # Description Qty Fuel Delivery System Rev J Diag # Description QtyGenerator Head Exploded View Rev J Ref # Description Qty