SIDE SLOPE EXCAVATING OR TRENCHING

Dig with the backhoe uphill whenever possible.

Level the backhoe on slopes with the stabilizers to dig plumb trenches, or use the backhoe or loader to cut a level slot for the uphill wheel and stabilizer. Pile the spoil from the slot on the low side.

When on the side of a steep slope, cut a level surface along the uphill side of the trench with the loader.

Pile the spoil of the cut downhill. When digging, pile the spoil of the trench uphill.

Dig field trenched progressively. As soon as one trench is completed, have the workmen lay the tile. Start the next trench, using the spoil to fill the previous trench.

MISCELLANEOUS

When finishing straight walls or bellholes in sandy soil, use a platform under the rear tires and the stabilizers. The plat- form distributes the load over a larger area and lessons the possibility of a cave-in. The platform also tends to keep the unit from creeping rearward if hard digging is encountered.

FINISHING STRAIGHT WALLS

Finish the far wall by crowding out while forcing the bucket down from the boom. Actuate the bucket (curl out) to keep the bottom of the bucket vertical.

To finish the near wall, lift up and crowd in. Keep the edges of the bucket horizontal.

BACKFILLING

Backfill by lifting the bucket over the spoil pile and then crowding in. Pull both the crowd and lift levers for smooth, even backfilling.

IMPORTANT: Do not backfill by using the swing circuit and dragging the bucket sideways. Doing so can cause damage to the dipperstick boom swing cylinders or mainframe.

13

Image 15
Contents Bush HOG Congratulations Backhoes Disclaimer of Implied Warranties & Consequential Damages This Limited Warranty Shall not Apply665H 765H 865H 965H Backhoes Dealer Preparation Check ListBackhoe TractorAdjustments and Inspection TransportationAvoid HIGH-PRESSURE Fluids Safety Decals Child Labor Under 16 Years Old Employee Tractor Operating InstructionsThis Act Seeks Osha RegulationsKeep bystanders a safe distance away Engine SpeedControls Page Transporting the Backhoe Placing the Stabilizers When TransportingDumping the Bucket Filling the BucketBackfilling Side Slope Excavating or TrenchingMiscellaneous Finishing Straight WallsHydraulic System Reservoir Beginning of SeasonBleeding Backhoe Hydraulic System Hydraulic System HosesTooth Replacement Tightening Nuts and BoltsLubrication Removal from Tractor Storage Install the swing safety lock pin as shown in Figures 1Stabilizer Pads 765H, 865H and 965H Hydraulic Trouble ShootingCauses and Corrections Replacing Spool Seals Replace Center Section AssembliesAssembly Hoe mainframe and swing frame to the skid at Be sure hoist Used is suitable, has suffiCient capacity and is in the proper position. Do Do not cut any strapping that fastens the backAssembly Refer to Figures 13 General Description Attaching KIT Instructions For 865HAssembly Hydraulic Hook-Up Closed Center System 665H &765H Backhoe Operation Hook-Up DiagramHydraulic Hook-Up 865H & 965H Hook-Up RequirementsAttaching KIT Instructions For 965H Assembly Refer to For Tractors with OPEN-CENTER Hydraulic Systems Tractor PreparationBackhoe Preparation Assembly of a Bush HOG Backhoe to a Bush HOG Loader Valve Bush HOG Backhoe & Bush HOG Loader Valve Assembly Outlet 11 .5 GPM PTO Pump KIT Assembly10 .5 GPM PTO Pump KIT Or 8 GPM PTO Pump KITPump Plate Positions GPM Pump KITSeries Models 665H and 765H Models 865H Shown 965H Page Bush HOG, L.L.C