Installation and Set-Up (Continued)
CENTERING GUIDES
1. Remove the two centering guides and four
M6 x 20 socket head screws from the package.
2. Using a 5 mm hex key wrench, attach the
centering guides to the rails with four M6 x 20
screws (two in each guide) as shown in
Figure 2-4.
Figure 2-2 – Infeed Conveyor
Figure 2-3 – Cover Plates
Figure 2-4 – Centering Guides
1. Remove the conveyor and the package of parts
from the carton.
2. Verify that the package contains two right
angled cover plates, twelve M8 x 15 hex head
screws, and eight M8 flat washers.
3. To assemble the infeed conveyor, refer to
Figure 2-2 and locate four bolt holes on the
infeed end of the case sealer frame.
4. Insert a M8 x 15 screw in each hole so that only
a few threads take hold. Do not use washers
with these screws.
5. Attach the infeed conveyor over the screws
using the inverted keyholes in the end of the
conveyor. Tighten all four screws with a 13 mm
wrench.
6. Refer to Figure 2-3. Set the cover plates over
the joint between the conveyor and the frame on
each side and secure them with four M8 x 15
screws and M8 washers.
INFEED CONVEYOR ASSEMBLY
14. Continue with the remainder of the Installation
and Set-Up procedure section.
13. Use appropriate material handling equipment to
remove the machine from the pallet and move it
into position.
Whenever the machine is lifted with a fork truck,
insure that the forks span completely across the
machine frame and do not contact any wiring or
mechanism under the machine frame. In some
cases the lower taping head may need to be
removed to avoid damage.
To reduce the risk associated with muscle
strain:
Use the appropriate rigging and material
handling equipment when lifting or
repositioning this equipment
WARNING