Mechanical Installation

A proper foundation is absolutely necessary for the UW50P-4 due to its high extract speed and the G-force exerted.

A bolt kit is available as an option consisting of eight 3/4 inch bolts, 8 inches long, which should be imbedded in a reinforced concrete floor that is a minimum of 12 inches thick.

0.75 in.

1

 

(19 mm)

2

 

3

2 in.

(51 mm)

8 in.

(203 mm)

4

5

TYPICAL METHOD OF MOUNTING USING

INDIVIDUAL MOUNTING BOLTS

PHM178N

NOTE: Existing floor must be a minimum of 12 inches thick.

1Machine Base

2Piece of Angle Welded to Bolt to Prevent Turning

3Grouting – 1/2 in. Thick

43/4 in.-10 x 8 in. Bolt

5Conical hole drilled or chiseled into existing floor. Fill with “Sulfaset” bolt or equivalent.

Figure 1

The threaded end of the bolts should extend 2 inches above the surface of the floor. Refer to Figure 3 for the location of these bolts. A bolt locator fixture (base frame), consisting of a rigid welded assembly made of reinforcing rod welded to the eight 3/4 inch bolts which may be embedded in the concrete as one piece is also available as an option. Refer to Figure 2. Be sure the bolt threads also extend 2 inches above the floor.

Installation

1

2

3

4

5

PHM179N

TYPICAL METHOD OF MOUNTING

USING BASE FRAME

PHM179N

1Machine Base

2Bolt Threads

3Grouting – 1/2 in. Thick

4Reinforcing Rod

53/4 in. x 8 in. Bolt

Figure 2

F232158

© Copyright, Alliance Laundry Systems LLC – DO NOT COPY or TRANSMIT

11