Installation

Overview

Warning: Review “Safety” on page 1 before starting this installation. Pay strict attention to all safety warnings and caution notices!

ALL INTERNAL cable connections were made prior to shipment.

EXTERNAL cable connections with the UPS need to be made on-site. EXTERNAL cable connections from the utility also need to be made on-site. EXTERNAL cable is not supplied.

Control wire connections between the UPS and the MBP additionally need to be made on-site. Control wires are not supplied.

Panel board breakers must be ordered separately. Tie-wraps are not supplied.

Tools

The following tools are required for this installation:

Dolly/hand-truck

M10 nut driver

Tape measure

Standard (flathead)

Pliers

Phillips screwdriver

Level

T30 Torx screwdriver

Marker

4mm Allen wrench

Drill

• 1/2” socket with ratchet

Panel board breakers

The 42-position panel board supports the following Square D® 1-, 2-, and 3-pole bolt-on circuit breakers. All of the circuit breakers listed below have been pre-tested and approved by APC.

Breaker Type

APC Part#

Breaker Type

APC Part#

1-pole, 20Amp

PD1P20ABBSD

3-pole, 20Amp

PD3P20ABBSD

 

 

 

 

2-pole, 20Amp

PD2P20ABBSD

3-pole, 80Amp

PD3P80ABBSD

 

 

 

 

2-pole, 30Amp

PD2P30ABBSD

3-pole, 100Amp

PD3P100ABBSD

 

 

 

 