APPENDIX A - FORMS
Stulz Air Technology Systems Inc.
Frederick, Maryland USA 21704
Telephone: (301)
❏1 Proper clearances for service access have
been maintained around equipment.
❏2 Equipment is level and mounting fasteners (if applicable) are tight.
❏3 Piping completed to refrigerant or coolant loop (if required).
❏4 All field installed piping leak tested.
❏5 Refrigerant charge added (if required).
❏6 Incoming line voltage matches equipment nominal nameplated rating ± tolerances.
❏7 Main power wiring connections to the
❏11 Foreign materials have been removed from
inside and around all equipment installed (shipping materials, construction materials, tools, etc.).
❏12 Compressors and pumps rotate freely without unusual noise.
❏13 Inspect all piping connections for leaks during initial operation.
equipment, including earth ground, have been properly installed.
❏8 Customer supplied main power circuit breaker
(HACR type) or fuses have proper ratings for equipment installed.
❏9 All wiring connections are tight.
❏10 Control wiring connections completed to
evaporator and condenser/condensing unit (if required), including wiring to wall mounted control panel and optional controls.