3.After the floor panels are installed and level, erect the partition wall panels.
4.After this the partition wall can be set in place and locked.
5.Position the remaining wall panels and lock them all down.
6.The top panels should be installed with the “Tee” Section first, then work toward the ends until all the tops are installed.
7.The combination
Figure #9
Lock access holes on reverse side
Penetrations of Panels
In some cases it will be necessary to make field penetrations through the
Panels can be penetrated with a drill bit or with metal shears for holes too large to drill. Seal around all lines after installation. These penetrations must be sealed on the outside as well as the inside of the hole with silicon to prevent moisture entering the
Membrane Roof Cap
Installation of Membrane Roof Cap (For Outside Units)
•Position single piece membrane over the
•Allow membrane to relax for 1/2 hour prior to any splicing, cutting, or flashing.
•Beginning with the long side of the box at the center, layout the 2x6 flashing provided for that side. Start the first piece 2 1/2" from the corner. Apply hand pressure until the 2" top break is approximately 90 degrees. Install the #6 self tapping screws (provided) into sidewalls as shown. Working toward the corners, continue pressure to the top of the flashing. Flashing will come to within 2 1/2" of the corner, which will be covered by the corner piece provided. (See Figure #13)