A.INSPECT SHIPMENT carefully for any signs of damage.

1.ALL EQUIPMENT is carefully manufactured, inspected and packed. Our responsibility ceases upon delivery of crated boiler to the carrier in good condition.

2.ANY CLAIMS for damage or shortage in shipment must be filed immediately against the carrier by the consignee. No claims for variances from, or shortage in orders, will be allowed by the manufacturer unless presented within sixty (60) days after receipt of goods.

B.LOCATE BOILER in front of final position before removing crate. See Figures 1A thru 1E.

1.LOCATE so that smoke pipe connection to chimney will be short and direct. BOILER IS SUITABLE FOR INSTALLATION ON COMBUSTIBLE FLOOR. Boiler cannot be installed on carpeting.

TABLE 2: Minimum Installation Clearances To Combustible Materials (Inches)

 

 

 

C

 

 

 

A

B

Chimney

D

E

Boiler

Above

Front

Connector

Rear

Sides

 

 

 

 

 

 

V7

6

24

18

6

6

 

 

 

 

 

 

2.FOR BASEMENT INSTALLATION, provide a solid base, such as concrete, if floor is not level, or if water may be encountered on floor around boiler.

3.PROVIDE SERVICE CLEARANCE of at least 24” on right side of boiler for removal of rear tankless heater. Provide at least 24” clearance from front jacket panel for servicing and removal of front tankless heater (increase to 30" for #A54 heater). Provide at least 24" clearance from right side of boiler or top of boiler for cleaning flueways. Boiler flueways may be cleaned either from the top or from the side.

4.For minimum clearances to combustible materials. See Table 2.

C.PROVIDE AIR SUPPLY AND VENTILATION to accommodate proper combustion. If natural ventilation is inadequate, provide a screened opening or duct from the boiler room to the outside. The opening or duct must be sized so the boiler input will not exceed 4,000 BTUH/Sq. In. of free area. If other air consuming appliances are near the boiler, the air inlet should be larger. Consult respective manufacturers.

NOTE 1: Listed clearances comply with American National Standard ANSI/NFPA 31, Installation of Oil Burning Equipment.

NOTE 2: V7 Series boilers can be installed in rooms with clearances from combustible material as listed above. Listed clearances cannot be reduced for alcove or closet installations.

NOTE 3: For reduced clearances to combustible material, protection must be provided as described in the above ANSI/NFPA 31 standard.