Install a sediment trap (drip leg) in the gas supply line, and then connect gas supply piping to the boiler gas valve piping.
line thoroughly before connecting it to the boiler. To ensure an adequate volume of steam, the branch steam supply line must be 3/~inch 'PS minimum. Connect the inverted bucket trap to the outlet end of the steam coil. Pill the trap with water before installing it. A permanent 115- volt electrical connection is required at the junction box. The junction box location is shown on the specification sheet. The installer must electrically ground the unit.
For Direct-Steam Connected Steamers and Kettles:
Connect steam supply piping to the input side of the line strainer. Location and pressure data are shown on the specification sheet. Flush the steam line thoroughly before connecting it to the steamer. To ensure an adequate volume of steam, the branch steam supply line must be 3/4 inch 'PSI 'minimum.
INSTALLATION CHECKS
Proper operation of the Cleveland Convection Steamer is dependent upon proper installation. After the steamer has been installed, a few quick checks could save unnecessary service calls.
1.The unit must be level.
2.The Convection Steamer requires a cold water connection for proper efficient operation. DO NOT USE HOT WATER. The cold water must be connected to the line strainer, located at the front lower right of the steamer base.
3.Check that the manual water supply valve is open.
For Electric-Powered Steam Generators: Connect
electric power: location and data are shown on the specification sheet. Provide connection as required by the unit, either directly to the single contactor, or to the terminal block (when equipped with multiple contactors). Electric supply must match power requirements specified on the data plate inside the base cabinet. The copper wiring size must be adequate to carry the required current at the rated voltage. A separate fused disconnect switch must be supplied and installed. The installer must electrically ground the unit
For Steam Coil Steam Generators: Connect steam supply piping to the input side of the steam coil. Location and pressure data are shown on the specification sheet. Incoming steam pressure must be regulated between 35 and 45 psi. A 3 /4inch strainer, equipped with a 20 mesh stainless steel screen, must be supplied and installed at the incoming steam connection point. Flush the steam
4.Check all water supply lines and valves for leaks.
5.Check that the water supply pressure and water quality meets the requirements of installation paragraphs.
6.On electrical units, verify that the supply voltage meets the voltage requirements on the rating plate inside the base cabinet and the voltage shown on the packing slip. Verify that the unit is protected with a separate fused disconnect and is properly grounded in accordance with the National Electric Code.
On gas, steam coil and
7.On all gas,
______________________________________________________________________________ 5