3-5.A/CHEADASS'YREMOVAL(See Fig.3-10)
a. Remove one nut hex from the A/C HEAD POST of the MAINBASE.
b. Remove the A/C HEAD ASSEMBLY from the MAINBASE.
c. Remove the A/C HEAD SPRING from the
A/C HEAD ASSEMBLY .
NOTE:
After reassembling, adjust the TAPE TRANSPORTING SYSTEM refering to chapter 5 "ADJUSTMENT OF THE TAPE TRANSPORTING SYSTEM".
After adjusting the TAPE TRANSPORTING SYSTEM, spread the A/C HEAD/NUT, AZIMUTH SCREW, and TILT SCREW with LOCKING PAINT.
3-6.L/CBRACKETASS'YREMOVAL(See Fig.3-11)
a. Remove one screw from the L/C BRACKET ASSEMBLY .
b. Remove the L/C BRACKET ASSEMBLY from the MAINBASE.
3-7.PINCHLEVER
TOTALASS'YREMOVAL(See Fig.3-11)
a. Remove one POLY WASHER from the PINCH LEVER POST of the MAINBASE.
b. Unhook the PINCH LEVER SPRING from the hook of MAINBASE and remove the
PINCH LEVER TOTAL ASSEMBLY .
CAUTION:
Take care not to coat GREASE, OIL or other substances on the surface of the PINCH ROLLER .
17