Delta 40, F-25, 35, 30, 45 Primary Piping, Notice, System Piping - Multiple Units Installation

Models: 45 30 35 40 F-25

1 57
Download 57 pages 26.34 Kb
Page 24
Image 24
System Piping - Multiple Units Installation

Primary Piping

NOTICE

 

NOTICE

 

 

 

If the radiant system tubing contains no oxygen barrier, a stainless steel heat exchanger must be used. Failure to install a heat exchanger could lead to premature failure of the outer tank and void any warranty claim.

WARNING

Radiant heating system piping should include a means of regulating the boiler return water. The return water tempera- ture to the unit should be maintained at 130ºF or higher. Failure to prevent low return water temperature to the unit could cause premature failure of the unit and it’s burner system resulting in severe personal injury, death or substantial property damage.

Size the system piping and circulator to pro- vide the flow needed for the radiant system.

To control the zone circulators refer to Fig. 19, page 35.

To ensure adequate flow rate through the ELITE, maintain a minimum 1 inch diameter on the system piping connect- ing the unit to and from the primary / secondary connection.

System Piping - Multiple Units Installation

Use a balance manifold system as the pri- mary / secondary connection to the space heating piping as shown in Fig. 12 page 23.

Refer to Fig. 7 page 20 to install air elimi- nation and expansion tank.

For the space heating piping refer to the applications mentioned in this manual or use recognized design methods.

NOTICE

To ensure adequate flow rate through the ELITE, maintain a minimum 1 inch diameter on the system piping connect- ing the unit to and from the primary / secondary connection.