Piping Connections and Piping Access Points
5.0PIPING CONNECTIONS AND PIPING ACCESS POINTS
Refer to site specific drawings for general locations of the piping connections. For Liebert XDCF con- nection locations, refer also to Figure 12.
5.1European Union Fluorinated Greenhouse Gas Requirements
Stationary air conditioning, refrigeration, heat pump equipments and stationary fire protection sys- tems in the European Community market and operating with fluorinated greenhouse gases
The
Refer to the full regulation for additional details.
5.2Connection Methods and Points
The assembly and connection means used for piping in the Liebert XD system are the same as those used in conventional refrigeration systems. Observe all standard practices during installation and startup to prevent damage and contamination.
Supply piping connection is 1/2" OD copper pipe, and return piping connection is 5/8" OD copper. Both supply and return fittings are
! CAUTION
Risk of sudden refrigerant discharge! Can cause loss of charge and minor injury!
Do not disconnect
The Liebert XDCF has supply and return piping access on the top of each module.
5.2.1Header System
The Liebert XDCF module system requires use of the Liebert XD prefabricated piping assembly. The prefabricated piping is compatible with the Liebert XD Flex Pipe required to attach to the Liebert XDCF modules.
Figure 12 Liebert XDCF supply and return piping access points
Return Pipe
(5/8" diameter)
(186mm)
(90mm) |
Supply Pipe (37mm) (1/2" diameter)
Pipe locations and dimensions are the same for upper and lower units
For additional information, refer to the Liebert Xtreme Density System Design Manual,
13