LOG SET ASSEMBLY:

Secondary Installation

LOG SET ASSEMBLY:

Figure 35. First Stage Log Set Installation

Figure 35: The first log to be placed is the front right log. The back end has a hole that sits on the right burner pin (see Figure 34) and the front has a notch that helps it rest on the center of the grate against one of the vertical bars. Second to be placed is the bottom log. The bottom log rests on the center and right ledge in the firebox (see Figure 34) and the large end must be flat against the right brick liner.

Figure 36: The back left log rests on the left ledge in the firebox (see Figure 34) and the left ledge on the bottom log (see Figure 35). The large end must be flat against the left brick liner.

Figure 36. Second Stage Log Set Installation

Figure 37: The top of the far left log has a hole that rests on the pin and ledge of the back left log (see Figure 36). The bottom of the far left log rests against the base of the left andiron. The top of the far right log has a hole that rests on the right pin and ledge of the bottom log (see Figure 35) and the bottom of the far right log rests against the base of the right andiron.

Figure 37. Third Stage Log Set Installation