Installation (cont’d)

Initial Energization (cont’d)

After all options and accessories are checked and verified, follow these steps to set up the ATS. Refer to Entelli-Switch 250 display Figure 4. The annunciation LEDs illuminate to indicate (1) source availability,

(2)ATS position, and (3) Entelli-Switch 250 control function (timing).

S 1 O K

2 1 : 5 6

M O N 2 3 A P R 2 0 0 2

M O R E T E S T

Figure 4 – LCD and keypad

1.Unlock the enclosure.

2.Open the enclosure.

3.Place the Disconnect Switch in the Inhibit.

NOTE: This step is only performed if the “DS” Option was purchased.

4.Close the external (up-stream) Source 1 circuit breaker.

NOTES: Source 1 Available and Source 1 Position LED’s will illuminate.

If Source 1 Available LED does not illuminate, verify that Source 1 Voltage is above the preset restore value.

The Gen-Set will start and run while

Source 2 stop Delay Timer is timing.

5.Close the External (up-stream) Source 2 line circuit breaker.

6.Start the engine generator in MANUAL mode.

NOTE: When the voltage and frequency reach preset values, the Source 2 Available LED will illuminate.

7.Verify the phase to phase voltages at Source 2 line terminals.

8.Verify that the phase rotation of

Source 2 is the same as the phase rotation of Source 1.

9.Shut down the generator's engine.

(Place in Automatic Mode.)

NOTE: Source 2 Available LED will turn off.

NOTE: The engine generator will continue to run for the duration of Source 2 Stop Delay Timer.

10.Place the disconnect switch to ENABLE.

11.Complete the visual inspection of the transfer switch.

12.Close the enclosure.

13.Lock the enclosure.

WARNING

When performing a hi-pot or

dielectric test on the power section,

DISCONNECT the control panel plugs from

the microprocessor to avoid potential damage.

GE Zenith Controls

Entelli-Switch 250 Operation and Maintenance Manual (71R-2000)

5

Page 5
Image 5
GE Entelli-Switch 250 manual Initial Energization cont’d, R E T E S T