8.Screw the push handles into the mast and tighten them.

9.Insert spreader bar attachment rod into spreader bar. Insert spreader bar rod into the U-bracket at the end of the boom. Align holes. Insert spreader bar attachment bolt and tighten.

10.Install the base adjustment handle in the socket located behind the mast sleeve on the base. With base handle to the far right position, insert and tighten base attachment bolt to ensure that the handle is firmly attached to the base.

11.LF1031 only: For shipping purposes, the boom is in its lowest position. To elevate, turn the pump knob clockwise until hand tight and operate the pump handle.

The LF1031 lift is now ready for use.

LF1041 lift: continue to next page.

install push handles

install spreader bar

install base adjustment handle

elevate boom

LF1031-INS-LAB-RevD12

10

Page 10
Image 10
Graham Field lf 1031 user manual LF1031-INS-LAB-RevD12