Piping Connection

Installation Procedure

Piping Connection

Connecting method

Connecting method Apply refrigerant oil at half union and flare nut.

Pipe cutting and flaring To bend a pipe, give the roundness as large as possible not to crash the pipe.

2.Arrangement of drain hose When connecting pipe, hold the pipe centre to centre then screw nut on by hand, refer to Fig. Piping connection of outdoor unit. Be careful not to let sundries, such as sands enter the pipe.

Pipe cutting and flaring

A

 

Vacuumizing Be sure to carry out deburring after pipe cutting with a pipe cutter.

Manual background Insert flaring tool to make a flare.

Forced fastening without centering may damage the threads and cause a gas leakage.

Flaring tool

 

Pipe dia.

Dimension A

 

Fastening torque

Liquid pipe

9.52mm (3/8")

1.0 ~ 1.8(mm)

32.7-39.9N.m

Gas pipe

19.05mm (3/4")

1.4 ~ 2.2(mm)

97.2-118.6N.m

Correct

 

Incorrect

 

 

Lean Damaged flare Crack

Partial Too outside

Piping connection of indoor unit 1.Arrangement of piping and drainage pipe

Manual background After opening inlet grill, you will see a control box as shown in the Fig. Remove the cover before wiring work.

Manual background Cut away, with a hammer or a saw, the lid for piping according to piping direction.

Manual background According to the piping method, connect the piping on indoor unit with union of connecting pipe.

Arrange the piping as per the wall hole and bind drain hose, connecting electric cable and piping together with polyethylene tape.

Insert the bound piping, connecting electric cable and drain hose through wall hole to connect with outdoor unit.

control box

Insulation material Copper tube

Drain hose

Connecting electric cable for indoor and outdoor unit

2.Arrangement of drain hose

Manual background Drain hose shall be placed in under place.

Manual background There should be a slope when arrange drain hose. Avoid up and down waves in drain hose.

Manual background If humidity is high, drain pipe( especially in room and indoor unit ) must be covered with insulation material.

Indoor unit

Slope

Up

Good

Down

Bad

Piping connection of outdoor unit.

Connect the connecting pipe and inlet / outlet liquid pipe according to the piping method.

Vacuumizing

Discharge the air out of the indoor unit and the refrigerant pipe by vacuumizing.

(1)Fasten all the nuts of the indoor and outdoor pipes to make these parts out of leakage.

(2)Under the condition of the complete close of the indoor and outdoor valve center (both liquid and gas side), dismount the service valve cap. Vacuumizing through the charge mouth of the service valve.

(3)After vacuumizing, fasten the service valve and dismount the cap of the big and small stop valve, then loosen the stop valve center completely and fasten the big and small stop valve.