2.Continue Adding Vent Components

Continue adding vent components, locking each succeed- ing component into place.

Ensure that each succeeding vent component is secure- ly fitted and locked into the preceding component in the vent system.

90° elbows may be installed and rotated to any point around the preceding component’s vertical axis. If an el- bow does not end up in a locked position with the pre- ceding component, attach with a minimum of two (2) sheet metal screws.

Figure 17. Adding Venting Components

3. Install Support Brackets

For Horizontal Runs - The vent system must be supported every five (5) feet of horizontal run by a horizontal pipe support.

To install support brackets for horizontal runs:

Place the pipe supports around the vent pipe.

Nail the pipe supports to the framing members.

For Vertical Runs - The vent system must be supported every eight (8) feet (2.4m) above the fireplace flue outlet by wall brackets.

To install support brackets for vertical runs:

Attach wall brackets to the vent pipe and secure the wall bracket to the framing members with nails or screws.

WALL BRACKET

WALL STUD

8 FT. (2.4m)

FLUE

OUTLET

1 INCH MIN. (25.4mm)

Figure 18. Installing Support Brackets

4. Install Firestops

For Horizontal Runs - Firestops are REQUIRED on both sides of a combustible wall through which the vent passes.

NOTE: Model DVK-01TRD does not need an exterior firestop on an exterior combustible wall.

To install firestops for horizontal runs that pass through either interior or exterior walls:

Cut a 12-inch by 12-inch (305mm X 305mm) hole through the wall.

NOTE: The center of the hole is one (1) inch (25.4mm) above the center of the horizontal vent pipe.

19

Page 19
Image 19
Heat & Glo LifeStyle BE-41 manual Continue Adding Vent Components, Install Support Brackets