2.Determine a location that is easily accessible for storage tank shutoff valve placement.

A.Measure the distance from storage tank connection point to desired shutoff valve location.

B.Cut off appropriate length of 3/8" tubing.

C.Insert 3/8" tubing into the push fitting on the tank adapter so that the tubing extends through the hole at the base of the tank.

D.Connect the supplied 3/8" ball valve (tank shut-off valve) to the other end of 3/8" tubing.

3.Place the tank in a location away from traffic. Ensure the selected area will support the weight of the tank when full (140lbs).

4.Run 3/8" poly tubing from the tank shut-off valve to the push connection at the bottom of the high pressure switch mounted on the left side of the RO filter system under the bracket and behind the sediment filter.

DRAIN CONNECTION

1.Insert supplied 1/4" tubing into the brine outlet port on the permeate pump.

NOTE: The drain line cannot be crimped or blocked.

2.Run tubing from brine outlet port to the drain using the least amount of tubing as possible.

3.Provide an air gap between end of drain tubing and drain.

4.Secure drain line in place using plastic ties.

NOTE: All local plumbing codes must be met when installing drain line.

EQUIPMENT CONNECTION

1.Insert 3/8" tubing into the outlet connection tee on the right side of the system. Run the minimum amount of tubing required to the inlet port of the equipment being fed.

NOTE: RO product water is only intended for misting and the equipment boiler/generator. Do not connect product water to the condensate line.

-7-