Site plan requirements and actions

Completing a site assessment

HP requires a detailed site assessment prior to planning and preparing the customer site location for the HP POD 20c. Consult with HP to schedule a site assessment.

A standard site assessment visit includes the following tasks:

Selecting an appropriate site for the HP POD 20c

Assessing the proposed site for: o Measurements for clearances

o Infrastructure for the final solution o Access to utilities

o Site pad

o Installation considerations, including locations for delivery trucks, large installation equipment (such as cranes), and storage

o Electrical infrastructure

o Chilled water infrastructure

o Facility network and access control systems

Developing an engagement plan and verifying customer contacts

Discussing future development and growth plans

For a complete site assessment checklist, see "Appendix A: HP site assessment (on page 25)."

HP Site Preparation Drawing Package

After receiving a signed purchase agreement, HP provides detailed engineering drawings. These drawings contain information to assist you and your MEP team to prepare the site for POD installation. If there are areas of special interest, HP can work directly with your MEP team to provide additional assistance.

Zoning and permit requirements

You are responsible for compliance of the overall installation in accordance with all local and national regulations, ordinances, codes, and the product specifications.

Project coordination

Your Project Manager must perform the following tasks:

Coordinate with all trades prior to installation to ensure that trade conflicts are resolved.

Coordinate the installation and integration of all systems.

Site plan requirements and actions 21