Item |
| Description | Initial |
|
|
|
|
2 |
| Verify that the chilled water supply temperature meets the minimum POD chilled water supply |
|
|
| temperature of 12°C (55°F). |
|
3 |
| Verify that a sufficient chilled water flow rate is available. |
|
4 |
| If necessary, verify that the |
|
|
| attained. |
|
Power Requirements |
| ||
|
|
| |
Item |
| Description | Initial |
|
|
|
|
1 |
| Verify that the short circuit analysis, arc flash, and circuit breaker coordination studies are |
|
|
| complete. Verify power work is completed according to the approved conduit routing |
|
|
| drawings that show the exact routes, plan view, sections, and elevations. |
|
2 |
| Verify that temporary site power for installation and construction is planned and available, if |
|
|
| applicable. |
|
3 |
| Verify that adequate site power exists per the HP POD 20c requirements. |
|
General |
|
| |
|
|
| |
Item |
| Description | Initial |
|
|
|
|
1 |
| Verify the utility connection to the HP POD 20c and any required metering equipment. |
|
2 |
| Verify the |
|
3 |
| Verify that the HP Project Team coordinates with other site construction activities. |
|