Ensure that the site safety and security programs are properly administered.

Interface directly with the HP installation project manager to ensure clear lines of communication during the installation and commissioning processes.

Site planning

A comprehensive site plan assists with the site design (MEP) and ensures the best possible HP POD 20c installation process. When creating a site plan, consider the following information:

HP POD 20c site requirements detailed in this document

HP POD 20c site preparation drawing package

HP POD 20c readiness checklist ("HP POD 20c site readiness checklist" on page 28)

HP POD 20c installation (on page 22)

The HP team can assist you by answering questions and help to guiding you throughout the process.

HP POD 20c installation

HP POD 20c installation includes the following:

Installation equipment staging (on page 22)

HP POD 20c lifting layout (on page 22)

HP POD 20c storage requirements (on page 23)

Additional structures (on page 24)

Installation equipment staging

Staging for the following items must be identified and considered:

Truck and component staging

Installation equipment staging

Site traffic

Regulatory or local permits

HP POD 20c lifting layout

When preparing a site plan, identify where to place the HP POD 20c and the equipment that is used for assembly. The following figure shows an HP POD 20c assembly site and includes:

HP POD 20c location

Crane location

Site plan requirements and actions 22

Page 22
Image 22
HP Performance Optimized Data Center (POD) 20cp manual Site planning, HP POD 20c installation