Item | Description | Initial |
|
|
|
|
|
10 | Verify that the site location has clearances for the HP POD 20c installation, including any |
|
|
| permanent structures, such as fences, walls, vestibules, and buildings. |
|
|
11 | Verify that all utilities, overhead and underground, are identified to maintain required |
|
|
| clearance. |
|
|
12 | Verify that there is adequate clearance around the HP POD 20c for door operation, |
|
|
| installation, and maintenance equipment. |
|
|
13 | Verify that the site location and site pads are marked for any transformer, external |
|
|
| switchboard, generators, and powerhouses. |
|
|
14 | Verify that the site has provisions for proper grounding and that the site location includes a |
|
|
| grounding electrode system. |
|
|
15 | Verify that the site location has adequate lighting for the HP POD 20c installation. |
|
|
16 | Verify that a truck and equipment staging areas are identified. |
|
|
17 | Verify the location for the fuel tanks for generators, powerhouses, and other equipment, if |
|
|
| applicable. |
|
|
18 | Verify the locations for cranes |
|
|
19 | Verify site access and clearances for equipment, including the crane and forklifts. A clear |
|
|
| path to the site must be maintained with clearance for all gates, headers, utility lines, and so |
|
|
| on. |
|
|
20 | Verify that the locations for storage and trash disposal are identified. |
|
|
21 | Verify that the safety equipment is planned for and in place in accordance with the |
|
|
| customer’s site safety program. |
|
|
22 | Verify the site interfaces and locations which connect to the fire alarm, access control system, |
|
|
| and communication system to the HP POD 20c to ensure that the POD can be properly |
|
|
| connected to the site BMS. |
|
|
23 | Verify that proper disposal methods are used for existing or potentially contaminated and/or |
|
|
| hazardous materials. |
|
|
24 | Verify the availability of security systems or equipment, including site fences, which are |
|
|
| required after construction. |
|
|
25 | Verify the availability of temporary facilities associated with the relocation of existing |
|
|
| services and operations. |
|
|
26 | Verify that all work relating to soil testing, removal, and site remediation is complete. |
|
|
27 | Verify that a temporary or permanent load bank is available, if applicable. |
|
|
28 | Verify the location of the EPO system external to the powerhouses, if applicable. |
|
|
29 | Verify the location of the remote electronic monitoring system. |
|
|
30 | Verify that |
|
|
| containers are complete at least one week prior to arrival of |
|
|
General Water Supply |
|
| |
|
|
| |
Item | Description | Initial |
|
|
|
|
|
1 | Verify that the site drainage is complete, and the HP POD 20c is not in a drainage path or |
|
|
| flood prone area. HP recommends placing the HP POD 20c on a raised site pad to prevent |
|
|
| water from entering the HP POD 20c. |
|
|
2 | Verify that the humidification water quality meets or exceeds these standards, which are |
|
|
| essentially drinking water standards. |
|
|
3 | Verify the humidification water supply isolation valve is installed for each POD. |
|
|
Chilled Water Supply |
|
| |
|
|
| |
Item | Description | Initial |
|
|
|
|
|
1 | Verify the chilled water supply and return headers are accessible, are in the appropriate |
|
|
| location, and are 80 cm (3 in) in diameter. |
|
|
| Appendix B: Preparing for delivery 29 |