CARBON MONOXIDE POISONING HAZARD
Failure to follow the steps outlined below for each appliance connected to the venting system being placed into operation could result in carbon- monxide poisoning or death.
The following steps shall be followed for each appliance connected to the venting system being placed into operation, while all other appliances connected to the venting system are not in operation:
1.Inspect the venting system for proper size and horizontal pitch. Determine that there is no blockage, restriction, leakage, corrosion or other deficiencies, which could cause an unsafe condition
2.Close all building doors and windows and all doors.
3.Turn on clothes dryers and TURN ON any exhaust fans, such as range hoods and bathroom exhausts, so they shall operate at maximum speed. Open the fireplace dampers. Do not operate a summer exhaust fan.
4.Follow the lighting instructions. Place the appliance being inspected in operation. Adjust thermostat so the appliance shall operate contin- uously.
5.Test each appliance (such as a water heater) equipped with a draft hood for spillage
6.After it has been determined that each appliance properly vents when tested as outlined above, return doors, windows, exhaust fans, fire- place dampers and any other gas burning appliance to their normal condition.
7.If improper venting is observed during any of the above tests, a problem exists with either the venting system or the appliance does not have enough combustion air (Supply Air from outside) to complete combustion. This condition must be corrected before the appliance can function safely.
NOTE: An unsafe condition exists when the CO reading exceeds 40 ppm and the draft reading is not in excess of - 0.1” w.c.
8.Any corrections to the venting system and / or to the supply (outside) air system must be in accordance with the National Fuel Gas Code Z223.1 or CAN/CGA B149.1 Natural Gas and Propane Installation Code (latest editions). If the vent system must be resized, follow the appropriate tables in Appendix G of the above codes or for this appliance.
12” minimum between bottom of air intake and any material below.
12” Min.
FIGURE 37: Attic and Crawl Space Combustion Air Termination
Specially Engineered Installations
The above requirements shall be permitted to be waived where special engineering, approved by the authority having jurisdiction, provides an adequate supply of air for combustion and ventilation.
Be sure to instruct the owner not to block this intake pipe.
VENT BLOWER ROTATION
For ease of venting, the vent blower may be rotated 90° in either direc- tion. For upflow installations the vent may exit through the top or either side of the cabinet. For downflow installations, the vent blower must be rotated so that the vent exits through either side of the cabinet. See Fig- ures
SECTION VIII: START-UP AND
ADJUSTMENTS
The initial
All electrical connections made in the field and in the factory should be checked for proper tightness.
When the gas supply is initially connected to the furnace, the gas piping may be full of air. In order to purge this air, it is recommended that the ground union be loosened until the odor of gas is detected. When gas is detected, immediately retighten the union and check for leaks. Allow five minutes for any gas to dissipate before continuing with the
28 | Johnson Controls Unitary Products |