ENGLISH

SECTION 2 - INSTALLATION

B.Stacking

For single ovens, skip ahead to Part C, Restraint Cable Installation.

IMPORTANT

Middleby Marshall STRONGLY RECOMMENDS that PS536GS oven cavities be stacked using the following:

PS500 Series Stacking Lift Kit, P/N 30580

PS536 Stacking Hardware Kit, P/N 46494

Contact your Middleby Marshall Authorized Service Agent for complete stacking instructions.

Figure 2-6 - Stacking

1.Stack an oven cavity on top of the lower oven. Check the following:

All four sides of the lower lip (on the bottom edge of the oven cavity) overlap the top of the lower oven.

The oven is level.

The oven is firmly seated.

See Figure 2-6.

2.For triple ovens, repeat Step 1 to install the top oven cavity.

3.Install the top panel using the screws included in the base pad kit, as shown in Figure 2-7.

Figure 2-7 - Top panel installation

#10 x 2"

screws

Top

C.Restraint Cable Installation

For CE-approved ovens, skip ahead to Part D, Conveyor Installation.

For domestic and standard export ovens, continue with this Section to install the restraint cable.

Because domestic and standard export ovens are equipped with casters, a restraint cable assembly must be installed to limit the movement of the appliance without depending on the connector and the quick disconnect device or its associated piping. One end of the cable is anchored to the eyebolt on one of the rear leg extensions, while the other is anchored to the wall. See Figure 2-8.

After connecting the restraint cable, move the oven to its final location. Then, lock the two front casters.

panel

Figure 2-8 - Installing the Restraint Cable

Restraint cable

assembly

3/8"-16 x 1" eyebolt on rear leg extension

3/4” (19mm)

eyebolt

Wall of

structure

10

Page 10
Image 10
Leupold PS536GS manual Stacking, Restraint Cable Installation