Completing Installation

INSTALLATION

Completing Installation

1.Remove any foreign material from inside the machine.

2.Check to assure scrap basket and sump cover are in place.

3.After plumbing and electrical connections are completed, check the machine for water leaks by depressing the ON/FILL switch on the front panel, then close and latch the door(s). This allows the tank to fill and to complete the rinse cycle. Check for leaks.

4.Open the door and check the water level. Water level should be at bottom of scrap screen.

5.Depress the OFF/DRAIN switch, close door, push start switch to drain the tank. This allows the machine to complete the wash and drain cycle. Check the drain plumbing for leaks.

6.Installation is now complete.

Indicates where properManual background water level should appear Manual backgroundManual background in the inlet chute area.