Normal Shutdown Procedure
To shutdown the generator use the following procedure:
1. Place both the MAIN, GFCI and LOAD circuit breakers
as shown in Figure 38 to the OFF position.
2. Place the engine speed switch (Figure 54) in the “

LOW

(down) position.
Figure 55. MPEC Control Switch (Off/Reset)
5. Verify that the

all

status LED on the MPEC display
are OFF (not lit).
6. Remove all loads from the generator.
7. Inspect entire generator for any damage or loosening of
components that may have occured during operation.
DCA-180SSV— GENERATOR SHUT-DOWN PROCEDURES
3. Let the engine cool by running it at low speed for 3-5
minutes with no load applied.
4. Place the
MPEC Control Switch
(Figure 55) in the
OFF/RESET position.
Figure 54. Engine Speed Switch (Low)
NEVER stop the engine suddenly except in an emergency.
WARNING -
SHUTTING DOWN THE GENERATOR
Emergency Shutdown Procedure
1. To stop the engine in the event of an emergency place
the
MPEC Control Switch
(Figure 55) in the
OFF/RESET position.