5-1SectionStartup Procedure
60
5-1 Startup Procedure5-1-1 Flowchart for Configuring and Checking the System
Check the following items when configuring the system.
SRM1
CompoBus/S transmission line wiring
Slave Unit
Power supply
connection
Node number
setting
SRM1 startup
I/O device
connections
End
CompoBus/S
communications
mode setting
No. Items to check Contents Reference
1CompoBus/S transmission
line wiring Is the CompoBus/S transmission cable securely connected,
and with no loose terminal screws?
Is the end of the transmission path (i.e., the farthest from the
SRM1) connected to a termination resistance?
Pages 23, 24
Also refer to the
CompoBus/S
Operation
Manual (W266)
2Power supply connection Is the wiring correct?
Are there any loose terminal screws?
Are there any short-circuited connectors?
Pages 23, 24
3Slave settings Is the bit allocation correct?
Have the node numbers been set properly, with no
duplication?
Page 8
4 Slave I/O connections Is the wiring correct?
Are there any loose terminal screws?
Are there any short-circuited connectors?
Refer to the
CompoBus/S
Operation
Manual (W266)
5 CompoBus/S
communications mode setting Is the CompoBus/S communications mode setting correct?
Manual (W266)