CUTTING AND FLARING THE PIPING
1.Please cut using pipe cutter and then remove the burrs.
2.Remove the burrs by using reamer. If burrs is not removed, gas leakage may be caused. Turn the piping end down to avoid the metal powder entering the pipe.
3.Please make flare after inserting the flare nut onto the copper pipes.
10.4 Evacuation Of The Equipment
WHEN INSTALLING AN AIR CONDITIONER, BE SURE TO EVACUATE THE AIR INSIDE THE INDOOR UNIT AND PIPES in the following procedure.
1.Connect a charging hose with a push pin to the Low side of a charging set and the service port of the gas side
2.Connect the micron gauge between vacuum pump and service port of outdoor units.
3.Turn on the power switch of the vacuum pump and make sure that connect digital micron gauge and to pull down to a value of 500 microns.
4.To make sure micron gauge a value 500 microns and close the low side valve of the charging set and turn off the vacuum pump.
5.Disconnect the vacuum pump house from the service port of the
6.Tighten the service port caps of gas side
7.Remove the valve caps of both of the
8.Mount valve caps onto the
o Be sure to check for gas leakage.
∙If micron gauge value does not descend 500 microns, take the following measures:
-If the leak stops when the piping connections are tightened further, continue working from step .
-If the leak does not stop when the connections are retightened, repair location of leak.
-Do not release refrigerant during piping work for installation and reinstallation.
-Take care of the liquid refrigerant, it may cause frostbite.
19