SmartNode 4520 & 4110 Series User Manual | G • Installation checklist |
|
|
Introduction
This appendix lists the tasks for installing a SmartNode 4520 or 4110 Series router (see table 15) . Make a copy of this checklist and mark the entries as you complete each task. For each SmartNode 4520 or 4110 Series router, include a copy of the completed checklist in your site log.
Table 15. Installation checklist
Task | Verified by | Date |
|
|
|
Network information available & recorded in site log |
|
|
|
|
|
Environmental specifications verified |
|
|
|
|
|
Site power voltages verified |
|
|
|
|
|
Installation site |
|
|
|
|
|
Required tools available |
|
|
|
|
|
Additional equipment available |
|
|
|
|
|
All printed documents available |
|
|
|
|
|
SmartWare release & build number verified |
|
|
|
|
|
Rack, desktop, or wall mounting of chassis completed |
|
|
|
|
|
Initial electrical connections established |
|
|
|
|
|
ASCII terminal attached to console port |
|
|
|
|
|
Cable length limits verified |
|
|
|
|
|
Initial configuration performed |
|
|
|
|
|
Initial operation verified |
|
|
|
|
|
Introduction | 78 |