7.OPERATION
7.1.Controls (Fig.6)
1Main switch.
Turn on the switch, led on, the machine is turned (apart from the boiler) and the pump is turned on to fill the boiler;
2Boiler resistance switch. Two-position switch with led.
On activating the switch, the led comes on, and power is supplied to the resistance for the boiler water.
3Coffee dispenser switch (mod. S1 - S1 TANK) On pressing the button, continuous coffee dispen- sing begins and the led comes on.
On
4Electronic coffee delivery button panel.(mod.
E1). Five buttons with relative led:
APress the button for a second, led on, release button; a small coffee is dispensed.
The led turns off and dispensing ceases.
BPress the button for a second, led on, release the button; a big cup of coffee is dispensed.
The led turns off and dispensing ceases.
CPress the button for a second, led on, release the button; two small coffees ar dispensed from the same unit.
The led turns off and dispensing ceases.
DPress the button for a second, led on, release the button; two big cups of coffee are dispensed from the same unit.
The led turns off and dispensing ceases.
EPress the button for a second, led on, release the button; coffee is continuously dispensed.
Press the button for a second, led off, release button; continuous dispensing of coffee ceases.
To interrupt dispensing taking place by pressing
5Hot water supply tap
Tap: turn in an anticlockwise direction to open and clockwise to close.
6Steam supply handwheel.
Tap: turn in an anticlockwise direction to open and clockwise to close.
7.2. Control instruments (Fig.6)
7Gauge with mobile needle on a fixed dial with a scale and colour indicator areas.
Visual control of the boiler pressure.
8Boiler water level indicator
9Tank water level indicator (Mod.S1 TANK)
7.3. Starting up (Fig.6)
Model S1
●Turn on the water supply tap 2 (Fig.5).
●Turn on main switch 1.
The pump for boiler filling will activate . Orange LED (8) ON
●When the level is reached, the pump stops, the LED switches OFF, turn the esistance switch 2; water is heated in the boiler; then, operate the unit until the water is dispensed.
●Wait for the machine to reach its working pressure, gauge needle 7, and to reach the correct thermal balance.
Model E1
●Turn on the water supply tap 2 (Fig.5).
●Turn on main switch 1 and resistance switch 2. The pump for boiler filling will activate Orange LED (8) ON
●Only after reaching the level (orange LED (8) ON) the resistances for water heating in the boiler are powered,then activate the group until water comes out.
●During the heating phase the leds of the keys switch on in sequence from left to right until the working pressure is reached.
Only when the rated pressure is reached it is possible to adjust the dosesl.
Model S1 TANK with autonomous tan
(Fig.7)
●Open the lid on the
●Ensure that the air trap C has been inserted in the appropriate housing;
If the air trap is not properly positioned, the machine may not heat or properly indicate the lack of water in the tank.
●Fill the tank with 2 litres of water and close the lid; Check the LED (9 - Fig.6)
●Turn on main switch 1; the boiler is filled and is activated.
Once the boiler is filled,turn resistance switch 2; the water is heated; then, operate the unit until the water is dispensed.
●Wait for the machine to reach its working pressure, gauge needle 7 - Fig.6, and to reach the correct thermal balance.
52