GT INSTALLATION AND OPERATION INSTRUCTIONS | Page 5 |
The GT condensing gas boiler is a high efficiency boiler utilizing induced power venting. It is designed to be vented directly to the outdoors using the venting methods and materials detailed in this section. The vent system must be both gas tight and watertight. All horizontal vent piping must be sloped back to the boiler a minimum of 1/4 in/ft, 21mm/m of vent.
NOTE: Steps must be taken to ensure that condensate does not collect in the venting system or the boiler will not operate properly.
This boiler may be vented using the following materials, but local codes must be followed:
•GT150 & 200: 3 in, 76 mm, PVC Sch.40 solid core pipe, CPVC Sch.40 pipe,
•
CAUTION: All vent systems must be fully supported by the building structure. The vent connection and vent piping MUST be perfectly aligned to the boiler connection, Figure 3. It MUST NOT APPLY ANY WEIGHT OR LATERAL FORCE TO THE FLUE BOX or the flue box will be damaged voiding the warranty!
Appropriate adapters must be used to increase the 2 in, 51 mm vent collar to 3 in, 76 mm at the boiler,
Figure 3- Vent Pipe To Boiler Attachment
The maximum combined equivalent vent and intake pipe lengths are listed in Table 2. The length specifi ed is the equivalent vent length added to the equivalent intake length.
Table 2 - Vent & Air Intake System Sizing
Model | Equivalent Combined Vent & Air Intake | |
Number | System Length (see note) | |
105 ft, 32 m | ||
105 ft, 32 m | ||
4" - 30 ft, 9 m | 6" - 65 ft, 20 m | |
50 ft, 15 m | ||
50 ft, 15 m | ||
4" - 30 ft, 9 m | 6" - 65 ft, 20 m |
Note: Subtract 5 ft, 1.5 m, for each 90° elbow except for the vent and air intake elbows. These don’t need to be considered. The length of the air inlet system must never exceed the length of the vent system. The vent system length may exceed the air inlet system length by no more than 20 equivalent ft, 6.1 equivalent m.
HORIZONTAL
DIRECT VENT SYSTEMS
Read the information in the GENERAL VENTING GUIDELINES section. It is recommended that two elbows be used, so that the 1/4 in/ft, 21mm/m slope of the horizontal vent system does not affect the vertical plumb of the pipe connected to the boiler, Figure 4.
Figure 4 - Vent System Attachment
When horizontal vent runs exceed 5 ft, 1.5m, they must be supported at 3 ft, 0.9 m, intervals with overhead hangers, 4 ft, 1.2 m for 6" pipe. The vent system must be pitched down, toward the boiler, 1/4 in/ft, 21mm/m. of vent. Structural penetrations must be made using approved thimbles.